The town of Norwood is set to review five alternate plans for the replacement of Norwood Junior High School, with architectural estimates expected to be completed this week. The building committee chairman, Richard W. Kief, expressed hope that a decision could be made at an upcoming special town meeting.
A special meeting of the building committee has been scheduled for tonight at 7:30 in Town Hall to review the various cost estimates and plans. If all information is received, it will be submitted to the School Committee, which would then select the best program educationally and economically. Dr. Thomas A. Couch, School Committee chairman, stated that his committee could make a decision the same night it receives the figures, possibly leading to a definitive decision on the new school project.
Meanwhile, town meeting member Mark Brim is researching federal reimbursement options for restoring Norwood Junior High School to its original condition. The town could receive 100 percent reimbursement for the damage excluding insurance under the “spot disaster law” administered by the Department of Health, Education and Welfare (HEW). Mark Brim has contacted HEW officials concerning the federal aid possibility, adding a new financial dimension to the town’s ongoing deliberations regarding educational infrastructure and disaster recovery.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Permanent School Building Construction Committee Votes to Proceed with Permanent Roof Plans for Burned-Out Junior High South and Aaron Guild School-September 15, 1972
School building construction committee votes to proceed with permanent roof plans for Junior High South and Aaron Guild School, while Endean Park junior high plans secure SBAB approval.

-
Work Under Way At Junior High North-May 29, 1970
In 1970, Norwood Junior High North saw new fencing, repaving, and drainage improvements while a major school facilities survey moved toward completion, shaping long‑term planning.

-
Norwood Kills Funds For School Addition-June 26, 1969
Voters approve a $1,000 Endean Park drainage compromise and reverse a zoning rule to relocate Carl A. Johnson’s Norwood Cadillac Co. along Route 1.

-
Strikes And Weather Delay North Junior High School Construction-June 17, 1969
Superintendent Warns Of Possible Double-Session Classes If Washington Street Facility Openings Fail A steel strike at the end of last summer halted installation of metal decking for the roof and delayed the roofer. Snow and freezing weather further hampered the project before the roof could be completed at the new school site. Without a roof,…

-
Parents Challenge Junior‑High Redistricting Plan-June 12, 1969
In June 1969, furious Cleveland School families took their grievances directly to town leaders, sparking a tense debate over school enrollment, modern facilities, and neighborhood identity.

-
Superintendent Coakley Tells PTA Council That $4 Million in New School Construction Is Mandatory-September 10, 1965
Dr. Philip O. Coakley tells the PTA Council that $4 million in new school construction—including a new elementary and junior high—is mandatory to handle over-capacity enrollment.