For Norwood High School’s 950 sophomores, juniors, and seniors, the current academic year has fallen woefully short of expectations. Displaced from their home campus because a $5 million renovation project failed to reach completion by the start of the term, students are currently holding classes at the former Junior High North.
“Most of the seniors I know are pretty ticked off,” said senior Jeffrey Lockwood. “It’s not like being a senior. I don’t like being here and I think most of the kids don’t like it.”
While the School Department initially planned to return students to the high school following the winter break in January, lagging construction progress has led some officials to speculate that students may be forced to remain at the junior high for the entirety of the school year.
Cramped Quarters and Heightened Security
In interviews conducted at the facility, students voiced deep frustration over the cramped conditions. Unlike the high school’s sprawling campus, which features five separate buildings connected by outdoor courtyards, Junior High North encloses students within a single structure.
“I think the junior high school is too crowded,” said senior Amy Sanderson. “We’re always rushing to get around. There’s no place to go outside to get some fresh air.” Sanderson added that the tighter confines foster a tense atmosphere: “I feel like we’re being watched over more closely than we were at the high school. It’s like we’re trapped.”
Assistant Principal George Usevich acknowledged that the smaller facility makes maintaining hallway order easier, but students viewed that tighter supervision with disfavor.
For the incoming sophomore class, the transition was doubly frustrating. Having just graduated from Junior High North before it closed in 1984 due to declining enrollment, students found themselves right back where they started. “I don’t like having to go back to a school that I went to for three years already,” said sophomore Amy Grove.
Impact on Athletics, Science Labs, and Library Resources
The disruption extends far beyond academics into extracurricular life. Inadequate athletic facilities at the North building mean the football team must board buses for practices at Junior High South playing fields. With the high school’s home fields undergoing reseeding, the team is playing without home-field advantage, dampening school spirit.
Superintendent James Savage noted that academic programs have been replicated as best as possible, but school leaders have openly lamented losses in specialized subjects. Chemistry and physics classes, for instance, suffer because indispensable laboratory equipment could not be fully reproduced at the junior high. Furthermore, the building’s library has been repurposed to house computer terminals rather than circulating books.
Seniors feel the sting most acutely, mourning the loss of traditional milestones associated with their final year.
“It’s not anyone’s fault,” Lockwood reflected regarding the delayed renovation, “but we get hurt the most by it.” Sanderson echoed the sentiment: “When I think about it, I get really mad. I never thought I would say I want to be back at the high school.”
(photo: 1986 TIOT)
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Norwood Voters Approve Tax Increase To Build New Coakley Middle School-April 10, 2022

Norwood residents delivered a decisive vote, choosing to raise local taxes in order to fund a long‑awaited new middle school. The ballot question passed by a wide margin — 2,365 to 831 — clearing the final hurdle required under Proposition 2½ for the town to take on additional debt. The vote followed a Special Town…
-
Norwood Adopts Whitman-Hanson School Prototype Model to Save Time and Money on New High School Construction-September 13, 2008

Norwood attempts to save time and money on its new high school construction project by reusing the architectural blueprints of Whitman-Hanson Regional High School.
-
Norwood School Officials Weigh Alternatives as Renovation Delays Threaten High School Opening-August 8, 1985

Norwood school officials discussed seven alternatives for opening day if $5 million high school renovations are not finished, while firmly rejecting double sessions.
-
Completion of Norwood High School Renovation Remains Uncertain-July 18, 1985

Town officials are uncertain if the $5 million Norwood High School renovation will be finished before the start of the fall semester.
-
Incomplete Sprinkler System Threatens Extended Half-Day Sessions at Norwood High School-September 9, 1976

Norwood High School may remain on half-day sessions due to incomplete sprinkler installation by ABC Sprinkler Co., prompting school committee threats of legal action.
-
Prospects Improve for On-Schedule Opening of Junior High South-July 26, 1974

Norwood’s Permanent Building Construction Committee received encouraging updates regarding material deliveries, clearing the path for Junior High South to open on schedule.
-
Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974

After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.
-
Unfinished Junior High To Open On Schedule-July 8, 1974

Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.
-
Permanent School Building Construction Committee Votes to Proceed with Permanent Roof Plans for Burned-Out Junior High South and Aaron Guild School-September 15, 1972

School building construction committee votes to proceed with permanent roof plans for Junior High South and Aaron Guild School, while Endean Park junior high plans secure SBAB approval.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.