Norwood High School’s $5 million renovation project will not be completed by the time classes are scheduled to resume on September 3, the project contractor informed town officials. Thomas Boyle, owner of Anchor Construction Co. of Lowell, stated during a joint meeting that the facility will not be ready for occupancy until October 15 at the earliest, citing persistent subcontractor issues and late material deliveries.
Major construction work remains incomplete on corridor floors and ceilings, heating and electrical systems, and critical safety infrastructure, including fire alarms and sprinkler systems, though most classroom work is finished. School Superintendent James Savage told the building committee that officials face costly decisions regarding temporary student housing, noting that the strongest alternative is utilizing the vacant Junior High School North. When building committee member Edward McDonough asked Boyle if he would bank on a September 3 opening, Boyle candidly replied, “No, in my opinion, if you can put those kids someplace else, put them someplace else.”
While construction supervisor Daniel Egan noted that 108 workers remain on site, missing key shipments—such as fire doors and heating ventilators—prevent building inspectors from granting occupancy. Committee members and project architect Richard Heydecker, along with high school Principal John Piccirilli and school committee Chairman Richard Kief, reviewed options including early dismissals or partial occupancy. However, Superintendent Savage cautioned that construction noise and uncompleted cafeterias would severely disrupt instruction, while Heydecker warned that environmental controls on the new heating system might remain unstable through January. The school committee scheduled a follow-up meeting to determine final student placement.
(Reporting by Bernie McEvoy, The Patriot Ledger).
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
Oldham School Opening Set for Wednesday, New Teacher Appointments-August 30, 1963

As Norwood prepares for the new academic year, the School Committee has announced plans to open the newly constructed John P. Oldham Elementary School next Wednesday, contingent upon final safety inspections of its heating and ventilating systems. While municipal electric light department crews rushed to finish electrical work and boilers were fired for the first…
-
Bios of New Norwood Public School Teachers-August 29, 1963

As the Norwood public school system prepares for the upcoming academic year, officials announced the appointment of 56 new teachers. Biographical profiles for the first 28 incoming educators highlight their educational backgrounds and assignments: High School Appointments Elementary, Junior High, and Special Services Appointments Discover more from Norwood Historical Society Subscribe to get the latest…
-
Superintendent Coakley Announces Upcoming Student Registration, New Teacher Orientation, and Summer Maintenance Progress-August 22, 1963

Norwood schools set registration dates and orientation schedules while summer maintenance projects wrap up across local buildings ahead of the September 4 opening.
-
Eight-Room Addition to Cleveland School Recommended Over New Construction-August 16, 1963

Voting 3 to 2, the Elementary School Building Committee recommended an eight-room addition to the Cleveland School over building a new facility, setting a joint meeting with Superintendent Philip O. Coakley.
-
School Building Committee Votes to Recommend Addition to Cleveland School-August 16, 1963

By a 3-2 vote, Norwood’s Elementary School Building Committee recommended an eight-room addition to the Cleveland School rather than constructing a new facility on Wilson Street.
-
Oldham School Building Committee Grapples with Defective Tile Work and Construction Delays-August 7, 1963

At a special meeting addressing 22 construction issues, the Oldham School Building Committee and architect George H. Stoner rejected 1,100 square feet of improperly installed exterior tile.⠀
-
Norwood Junior High Aerial View-October 9, 1957

Norwood Junior High Aerial View-This Day In Norwood History-October 9, 1957
-
Movement Underway Here For Public Kindergarten-November 7, 1946

Movement Underway Here For Public Kindergarten-This Day in Norwood History-November 7, 1946
-
School Board Studies Hockey Rink For School, New Schools, Sets New Weather Policy-This Day in Norwood History-June 30, 1946

The Norwood School Committee institutes a firm new inclement weather academic policy, launches cost evaluations for a high school hockey rink, and updates educational equipment for the local schools.
-
Father Sues Town for $15,000 Because Proper Conveyance is Not Provided to School-November 22, 1895

WANTS HIS CHILDREN CARRIED. This town is all in a ferment again over the so-called Gillin case. Away back in 1889 Rev George Hill, who was then chairman of the school board of Norwood, authorized Mr. James J. Gillon, who resides near the Dedham borderline and three miles from the nearest normal school house, to…
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.