The Norwood Permanent Building Committee announced that six architectural firms have been invited to submit proposals and participate in September interviews for the major renovation of the Guild School into a new community recreation center. Committee Chairman Roger Pellitier noted that the firms responded directly to advertisements placed in professional publications, though additional firms may still be considered.
The six competing architectural firms asked to submit proposals are:
- Drummey Rosane Anderson of Newton
- Korslund, LeNormand & Quann Inc. of Norwood
- Brian G. Novack Associates of Norwood
- Campbell & Searson of Cambridge
- TAMS of Boston
- Rich, Lang & Cote Inc. of Newton
Eliot Field Renovation and Recreation Scheduling
In related municipal recreation updates, the contract to design and oversee the renovation of Eliot Field in South Norwood—which is slated to replace the existing Civic Center field—has been awarded to Norwood Engineering.
With Norwood Hospital scheduled to take over the current Civic Center field property next summer, local residents and sports leagues raised concerns regarding potential field shortages for the upcoming baseball season. However, Pellitier assured the community that the recreation department has successfully arranged to reschedule affected games to alternative fields. Furthermore, Pellitier explained that the extended timeline will benefit the project: “Eliot Field will have an extra growing season after renovations are complete,” with the new facility expected to open in the spring of 1982.
To fund the physical construction of both the Guild School recreation center and the Eliot Field upgrades, officials anticipate that a special town meeting will be called later in the fall to appropriate the necessary capital funds.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
DPW Adds Safety Measures At Route 1A Detour Site / Group Cites Need For New School-November 6, 1964

Following fatal crashes, DPW crews added reflectorized lines and signage to the Route 1 detour in Sharon, while Norwood residents debate a $525,000 Morrill Memorial Library addition and Cleveland School petition.
-
Oldham School Drainage Repairs Scheduled For Completion-June 24, 1964

Corrective Measures Target Long-Standing Controversy At Elementary Site Corrective measures designed to resolve persisting drainage problems at the Oldham Elementary School are scheduled to be completed by the end of this week. The ongoing drainage difficulties at the new school site had been the subject of a long controversy in discussions of the Oldham School…
-
Parking Proposals in Norwood-July 31, 1963

The Patriot Ledger’s July 31, 1963 edition brought forth a plethora of news stories that captivated the residents of Norwood and surrounding areas. Among these was the Parking Commission’s meeting with the Board of Selectmen to discuss proposals for acquiring land for parking purposes. This pivotal discussion took place in an executive session, which raised…
-
Winslow Train Station Abolished, Leading to Construction of Subway Hill-This Day In Norwood History- July 17, 1891

This Day In Norwood History- July 17, 1891-Winslow Train Station Abolished, Leading to Construction of Subway Hill
-
The Town Reservoir and Water Towers- 1890

1890- The Commissioners beg to renew the recommendation of a former Board, and strongly urge the town to lay a six-inch main pipe from the corner of Winter and Prospect Sts., to connect with the main pipe on Cottage Street. This connection by continuous pumping will ensure the town a supply of water, in case…