NORWOOD — An eleventh-hour session of the Oldham School Building Committee is being held tonight to make the decisive call on whether the newly constructed school will officially open its doors for student registration tomorrow morning.
Final Scramble and Boiler Inspections
Workmen labored through the weekend, including a full day on Saturday, trying to wrap up numerous minor finishing tasks alongside major repair and painting demands insisted upon by the building committee, whose members conducted a thorough inspection of the premises over the weekend.
Of prime concern to both the school committee and the building committee is official approval of the school’s heating system. Boiler safety tests—originally scheduled for Friday—were forced to cancel due to a lack of electric power, which was finally restored on a temporary basis Friday by employees of the Norwood Light Department following a spirited push by committee members to accelerate lagging construction. A representative from the Department of Public Safety was slated to arrive at the Prospect Street school for the boiler test, as state occupancy approval is mandatory before the school can open. Additionally, the Norwood Fire Department must sign off on vital safety factors, including the heating system.
Unfinished Construction and Dissenting Voices
The greatest concentration of unfinished work centers on the kindergarten rooms, which were originally scheduled to open Monday, along with uninstalled carpeting in the principal’s office, teachers’ rooms, and the library, plus considerable interior and exterior tile work. Furthermore, about 1,600 square feet of tile flooring deemed “unsatisfactory” by the building committee must be replaced by general contractor Goverman at their own expense, though Clerk of the Works William Snyder reported that replacement work will be conducted in stages to avoid an unsightly appearance.
Despite Building Committee member Arthur Rodgers and Mrs. Ellen Dixon strongly opposing opening the school under any unfinished conditions—even discussing involving the bonding company—the building committee ultimately voted unanimously during its Wednesday night meeting to proceed with plans to open. Clerk of the Works Snyder privately expressed his opinion that the building is still roughly two to three weeks away from being fully complete.
Meanwhile, school department custodians worked feverishly over the weekend moving furniture into classrooms and conducting a deep cleaning. While exterior landscaping, hot-top walkways, and driveways are nearly finished, much of the remaining site work and classroom tile replacement will be handled after school hours. If the heating system passes state and local inspections, approximately 450 students are expected to walk through the doors tomorrow morning.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
School Board Recall Urged-July 8, 1978

Discover the 1978 budget battle in Norwood, where deep cuts to the school district’s $11.3 million budget led to a controversial recall effort and a lawsuit involving the Massachusetts Teachers Association.
-
Taxpayers Sue to Restore School Budget-July 6, 1978

Seeking to prevent a mid-summer school closure, 36 Norwood taxpayers filed a lawsuit in 1978 to restore $600,000 in education funding.
-
Henry O. Peabody School Hosts Fifth Annual Harvest Fair and Flea Market-October 15, 1977

The Henry O. Peabody School for Girls holds its fifth annual Harvest Fair featuring food booths, crafts, flea market treasures, and student fundraiser activities.
-
Willett School PTA Launches Petition Drive to Fight Potential School Closure-October 11, 1977

Facing declining student enrollments across Norwood, the Willett School PTA initiates a petition drive to keep their school open, while school officials weigh options.
-
New Teachers Association President Richard T. King Focuses on Students and Educational Priorities Over Dollars-September 25, 1977

Newly elected Norwood Teachers Association President Richard T. King outlines a cooperative agenda focused on educational issues, special needs training under Chapter 766, and student scholarship programs.
-
Town Requests Bids for Audio-Activated Alarm System Trial at George F. Willett School-August 31, 1977

Seeking proactive solutions to combat recurring vandalism, the town manager’s office has officially requested bids for furnishing and installing an advanced audio-activated alarm system at the George F. Willett School on Westover Parkway. Trial Security System Specifications According to municipal procurement notices, sealed bids will be publicly opened at 11:00 a.m. on September 14 in…
-
Public Schools Announce 1977-78 Opening Schedules and Projected Enrollment of 5,842 Students-August 31, 1977

Superintendent of Schools Philip O. Coakley has officially announced that all Norwood public schools-covering grades 1 through 12, alongside special education classes-will open for the 1977–78 academic year on Wednesday, September 7. Registration is open daily in each school building from 9:00 a.m. to 3:00 p.m. ahead of opening day, with classrooms prepped for an…
-
Norwood Zeroes In On School Vandals-August 3, 1977

A newly formed blue‑ribbon security committee convened to confront a surge of costly vandalism at Norwood’s public schools. Members reviewed structural, technological, and community‑based deterrents while assigning formal research duties for a comprehensive townwide response.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.