NORWOOD — An eleventh-hour session of the Oldham School Building Committee is being held tonight to make the decisive call on whether the newly constructed school will officially open its doors for student registration tomorrow morning.
Final Scramble and Boiler Inspections
Workmen labored through the weekend, including a full day on Saturday, trying to wrap up numerous minor finishing tasks alongside major repair and painting demands insisted upon by the building committee, whose members conducted a thorough inspection of the premises over the weekend.
Of prime concern to both the school committee and the building committee is official approval of the school’s heating system. Boiler safety tests—originally scheduled for Friday—were forced to cancel due to a lack of electric power, which was finally restored on a temporary basis Friday by employees of the Norwood Light Department following a spirited push by committee members to accelerate lagging construction. A representative from the Department of Public Safety was slated to arrive at the Prospect Street school for the boiler test, as state occupancy approval is mandatory before the school can open. Additionally, the Norwood Fire Department must sign off on vital safety factors, including the heating system.
Unfinished Construction and Dissenting Voices
The greatest concentration of unfinished work centers on the kindergarten rooms, which were originally scheduled to open Monday, along with uninstalled carpeting in the principal’s office, teachers’ rooms, and the library, plus considerable interior and exterior tile work. Furthermore, about 1,600 square feet of tile flooring deemed “unsatisfactory” by the building committee must be replaced by general contractor Goverman at their own expense, though Clerk of the Works William Snyder reported that replacement work will be conducted in stages to avoid an unsightly appearance.
Despite Building Committee member Arthur Rodgers and Mrs. Ellen Dixon strongly opposing opening the school under any unfinished conditions—even discussing involving the bonding company—the building committee ultimately voted unanimously during its Wednesday night meeting to proceed with plans to open. Clerk of the Works Snyder privately expressed his opinion that the building is still roughly two to three weeks away from being fully complete.
Meanwhile, school department custodians worked feverishly over the weekend moving furniture into classrooms and conducting a deep cleaning. While exterior landscaping, hot-top walkways, and driveways are nearly finished, much of the remaining site work and classroom tile replacement will be handled after school hours. If the heating system passes state and local inspections, approximately 450 students are expected to walk through the doors tomorrow morning.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Unfinished Junior High To Open On Schedule-July 8, 1974
Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.

-
School Board Rejects ‘Floating Principal’ Proposal-July 03, 1974
The Norwood School Committee held a contentious session on the evening of July 2, 1974, where, following two weeks of deliberation and a lengthy 90-minute executive session, the board voted 5-1 to reject a proposal to create a new administrative position titled “floating principal.“ The concept, initially championed by Committee Member Joseph M. Pentowski, was…

-
School Drop-In Centers Possible In Fall-June 24, 1974
Citing summer custodial constraints and a lack of air conditioning, town officials vote to survey local youths during the summer to prepare for a fall launch.

-
Public Schools Face Delays and Possible State Action on Mandatory Hot Lunch Program-August 31, 1973
Parents of elementary school students in Norwood will need to continue packing brown-bag lunches for the start of the academic year. School Superintendent Philip O. Coakley announced that the town will fail to meet the state-mandated September deadline for implementing a universal public school hot lunch program, exposing the municipality to potential legal action by…

-
School Board Reverses Vote, Keeps NorWest Woods Pupils at Oldham-August 29, 1972
In a reversal of a previous decision, the School Committee has voted to keep 46 elementary school children from the Nor-West Woods apartment complex at the Oldham School, rescinding a July 5 vote that would have transferred them to the Shattuck School. Superintendent Dr. Philip O. Coakley explained that the committee revoted on the matter…

-
Norwood Sets $38 Tax Rate on Court-Ordered 100% Property Valuation for 1972-August 16, 1972
Announcing a 1972 tax rate of $38 per $1,000 under a court-ordered 100 percent property valuation, Assessor Chairman James J. Drummey concluded a major reassessment by Cole, Layer and Trumble.

-
Schools Face Heating Oil Shortage for Upcoming Winter, While Band Camp and Library Art Programs Make Headlines-August 6, 1970
Superintendent Dr. Philip O. Coakley informed the Norwood School Committee that no companies submitted bids to supply 110,000 gallons of No. 5 heating oil for town schools due to quotas, shortages, and environmental regulations.

-
Bells Are Ringin’-July 3, 1970
The Norwood School Committee overhauled its student transportation system and faced an $8,000 wave of structural school vandalism in July 1970

-
Almost 50% of Graduates Head To College-July 10, 1969
The Norwood High School guidance department released a significant report on July 10, 1969, detailing the educational future of the school’s 419 graduates. The data revealed that approximately 45 percent of the class planned to attend four-year colleges that fall, a figure the department noted was likely the highest percentage of four-year institution acceptances in…

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.