NORWOOD — An eleventh-hour session of the Oldham School Building Committee is being held tonight to make the decisive call on whether the newly constructed school will officially open its doors for student registration tomorrow morning.
Final Scramble and Boiler Inspections
Workmen labored through the weekend, including a full day on Saturday, trying to wrap up numerous minor finishing tasks alongside major repair and painting demands insisted upon by the building committee, whose members conducted a thorough inspection of the premises over the weekend.
Of prime concern to both the school committee and the building committee is official approval of the school’s heating system. Boiler safety tests—originally scheduled for Friday—were forced to cancel due to a lack of electric power, which was finally restored on a temporary basis Friday by employees of the Norwood Light Department following a spirited push by committee members to accelerate lagging construction. A representative from the Department of Public Safety was slated to arrive at the Prospect Street school for the boiler test, as state occupancy approval is mandatory before the school can open. Additionally, the Norwood Fire Department must sign off on vital safety factors, including the heating system.
Unfinished Construction and Dissenting Voices
The greatest concentration of unfinished work centers on the kindergarten rooms, which were originally scheduled to open Monday, along with uninstalled carpeting in the principal’s office, teachers’ rooms, and the library, plus considerable interior and exterior tile work. Furthermore, about 1,600 square feet of tile flooring deemed “unsatisfactory” by the building committee must be replaced by general contractor Goverman at their own expense, though Clerk of the Works William Snyder reported that replacement work will be conducted in stages to avoid an unsightly appearance.
Despite Building Committee member Arthur Rodgers and Mrs. Ellen Dixon strongly opposing opening the school under any unfinished conditions—even discussing involving the bonding company—the building committee ultimately voted unanimously during its Wednesday night meeting to proceed with plans to open. Clerk of the Works Snyder privately expressed his opinion that the building is still roughly two to three weeks away from being fully complete.
Meanwhile, school department custodians worked feverishly over the weekend moving furniture into classrooms and conducting a deep cleaning. While exterior landscaping, hot-top walkways, and driveways are nearly finished, much of the remaining site work and classroom tile replacement will be handled after school hours. If the heating system passes state and local inspections, approximately 450 students are expected to walk through the doors tomorrow morning.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Norwood Zeroes In On School Vandals-August 3, 1977
A newly formed blue‑ribbon security committee convened to confront a surge of costly vandalism at Norwood’s public schools. Members reviewed structural, technological, and community‑based deterrents while assigning formal research duties for a comprehensive townwide response.

-
Norwood School Committee Seeks Field Trip Funds and Awards Bus Transportation Contracts-July 29, 1976
Facing budget cuts that eliminated student field trips, the Norwood School Committee voted to appeal to the Finance Commission and special town meeting for restoration funds.

-
Norwood Board Rejects Blue Hills Collaborative-July 29, 1976
The summer of 1976 was a time of great change and uncertainty for the town of Norwood, Massachusetts. As the nation celebrated its bicentennial, local residents were grappling with issues of education, finance, and community involvement. One such issue that dominated the headlines in July 1976 was the proposed Blue Hills Collaborative, a vocational school…

-
Norwood School Committee Approves Balch School Remedial Class and Eight-Period High School Day-July 31, 1975
The Norwood School Committee approved a pilot transitional first grade and modified kindergarten at Balch School to address kindergarten screening results and language needs.

-
School Committee Approves Shortened High School Day Format-July 16, 1975
The school committee of Norwood last night all but formally approved a switch to a shorter, eight-period day for the high school. The decision was made in response to a request from absent member Richard Joseph, who asked that the board defer its official vote on the plan until its next regular meeting in two…

-
Youth Enriched at Summer School-August 13, 1974
Directing over 600 local students, Norwood’s public summer school program completed its 30-day session, highlighting strong popularity for enrichment classes in arts and trades alongside vital remedial and special education tutoring.

-
Norwood School Committee Votes to Relocate School Administration Offices-August 1, 1974
The Norwood School Committee voted 5-2 to relocate central school administration offices to the Winslow School, pending cost estimates from Superintendent Philip O. Coakley.
-
Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974
After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.