Meeting under the active leadership of Committee Chairman Ernest Paciorkowski, the Norwood permanent building construction committee voted during its latest session to undertake the immediate reroofing of the Aaron Guild School. The decisive vote came following urgent recommendations from architectural professionals hired to oversee the complex conversion of the fire-damaged former junior high school building into a modern elementary facility. The architects strongly advised the committee to completely execute the roof replacement prior to the onset of freezing winter weather to prevent further weather-related deterioration of the interior classrooms.

Independent Roofing Contract and Skylight Elimination

Chairman Paciorkowski urged prompt administrative attention, pointing out that the critical roofing work must be handled under a separate, independent contract distinct from the major $1.3 million school conversion project. Before preparing the formal roofing contract specifications, committee members and school administrators must first secure official approval from the state School Building Assistance Bureau (SBAB). School officials scheduled meetings with SBAB representatives to review the project scope.

Acting upon a specific motion introduced by committee member Richard W. Kief, the committee voted unanimously to eliminate all skylights from the newly designed roof structure unless architects discover overriding safety code regulations that strictly mandate their retention. Committee members concurred that removing the skylights would significantly streamline the visual appearance of the new roof while simultaneously lowering long-term municipal maintenance costs.

The committee’s vote followed structural recommendations presented by architect James McGrath of the firm Korslund, LeNormand and Quann, who proposed knocking down the damaged third-floor exterior walls down to the second-story level, reframing them entirely, and constructing the new roof from that baseline. McGrath noted that the temporary roof erected the previous autumn to protect the building’s interior had proven entirely inadequate, resulting in visible deterioration across several classrooms and existing skylights. McGrath estimated that the roofing project plans were already 90 percent complete and could be fully ready within a week. He further projected that once the plans cleared the SBAB and went out to bid, the actual physical roofing work could be successfully accomplished in approximately eight weeks, well before winter set in.

Endean Park Junior High Design Revisions and Athletic Field Costs

Shifting attention to the separate $6 million new junior high school project planned at Endean Park, Chairman Paciorkowski announced that sealed bids for the main construction contract would be publicly opened on October 12, with subcontractor bids following in late October rather than September as initially forecasted. Groundbreaking for the major facility is officially anticipated to take place in late October.

However, architect James McGrath delivered some difficult financial news regarding site preparation for the Endean Park campus. Due to a severe local shortage of native topsoil on the property, contractors would need to import roughly 5,170 cubic yards of loam, carrying an estimated price tag of $28,850. Instead of applying the standard six inches of loam to be seeded, McGrath recommended utilizing high-quality grass sod laid over four inches of base loam, which would raise the total cost to $40,465 (an additional increase of $2,200). Superintendent Philip O. Coakley advocated strongly for the sodding alternative, explaining that it would allow three of the school’s athletic fields to be ready for immediate student use by September 1974—coinciding with the targeted opening date of the new school—while saving significant maintenance and seeding expenses in the long run.

The committee also reviewed revised architectural floor plans for the Endean Park project, which featured adjustments to the kitchen-cafeteria layout and a proposed reversal of the administrative offices and the instructional media center to enhance overall building security, an idea originally championed by Richard Kief. While the layout shift would reduce the media center’s footprint by 500 square feet, committee member Joseph P. Olshan requested cost estimates for flooring over the relocated office area to create a two-story layout with additional rooms above, prompting Superintendent Coakley to remark, “We can always use more space.”

Furthermore, committee member Richard Kief raised sharp objections regarding an unannounced specification change made by Health Agent Bartley J. King, who rejected planned plastic piping for the athletic fields’ underground watering system in favor of mandatory asbestos cement pipe. Kief expressed strong frustration that specifications were altered without committee consultation, noting a major distinction between interior residential plumbing codes and exterior athletic grounds watering. The architect was directed to prepare an alternate plan utilizing the plastic piping for committee review, alongside separate alternative plans omitting classroom partitions estimated to cost around $50,000.

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Work Under Way At Junior High North-May 29, 1970

    In 1970, Norwood Junior High North saw new fencing, repaving, and drainage improvements while a major school facilities survey moved toward completion, shaping long‑term planning.

  • Norwood Kills Funds For School Addition-June 26, 1969

    Voters approve a $1,000 Endean Park drainage compromise and reverse a zoning rule to relocate Carl A. Johnson’s Norwood Cadillac Co. along Route 1.

    Open ledger titled County Ledger 1969 with budget requests marked 'Budget Cut' and a judge's gavel on a wooden desk
  • Strikes And Weather Delay North Junior High School Construction-June 17, 1969

    Superintendent Warns Of Possible Double-Session Classes If Washington Street Facility Openings Fail A steel strike at the end of last summer halted installation of metal decking for the roof and delayed the roofer. Snow and freezing weather further hampered the project before the roof could be completed at the new school site. Without a roof,…

  • Parents Challenge Junior‑High Redistricting Plan-June 12, 1969

    In June 1969, furious Cleveland School families took their grievances directly to town leaders, sparking a tense debate over school enrollment, modern facilities, and neighborhood identity.

  • Willett School Wiring Dispute Adds $9,000 to Construction Costs Ahead of September Opening-July 28, 1968

    ⠀ The Norwood Permanent Building Construction Committee last night voted to approve the installation of additional circuit breaker panels so that the Willett School can open on schedule in September. The cost of the electrical installation is estimated at approximately $9,000. William J. Kates, supervisor of the Municipal Light Department and inspector of wires, advised…

  • Ground Broken for $1.23 Million George F. Willett Elementary School-August 11, 1967

    Following a $1.04 million contract award and emergency state borrowing approval, Rocheford Construction Co. broke ground on the 16-classroom George F. Willett Elementary School.

  • School Building Committee Votes to Recommend Addition to Cleveland School-August 16, 1963

    By a 3-2 vote, Norwood’s Elementary School Building Committee recommended an eight-room addition to the Cleveland School rather than constructing a new facility on Wilson Street.

  • School Committee Considers New School Sites-March 22, 1962

    NORWOOD, Mar, 22 -Arthur B. Rodgers, chairman of the School Housing Study Committee which is responsible for the long-range projection of the towns future school needs, has requested information from the School Committee on its plans for new schools. Being considered by the School Committee are the possibilities of the construction of a second junior…

  • Redecorating Of School Interiors Is Recommended-February 9, 1950

    Purchase Of Land For New Stands At High School Also Urged By Supt. Lynch Recommendations for the improvement of the present school plant before the town faced with the problem of new construction were advanced by School Superintendent Lincoln D. Lynch, as principal speaker at the February meeting of the Chamber of Commerce Tuesday night…