The Norwood Building Code Board of Appeal issued a decisive ruling on the evening of July 10, 1975, unanimously rejecting a formal request by George Whitten to waive a mandatory firewall requirement at his commercial warehouse on Oceana Drive.

The sprawling building represents one of two major warehouse facilities owned by Whitten within the industrial University Avenue development zone. At the time of the hearing, the facility housed two distinct commercial tenants: United Liquors and the Olympic Adhesives Company.
⠀
Under the provisions of the town’s zoning parameters, the adhesives corporation is explicitly categorized as a manufacturing facility, whereas the liquor distribution company leases its designated sector purely for storage operations. Because the structure housed a “mixed occupancy,” Town Building Inspector John E. Grover ruled that the adjacent quarters of the two businesses must be physically separated by a formal three-hour rated firewall. A basic corrugated metal partition was the only structure dividing the two commercial spaces at the time. Whitten and his project engineer, William Merry, challenged Grover’s interpretation of the state building rules, asserting that neither firm would require a three-hour firewall if they operated as the sole occupant of the property, and therefore the requirement should not apply to the shared layout. They also presented data showing that Olympic Adhesives utilized water-based glues that were officially categorized as a low-hazard risk by their corporate insurance provider.
⠀
However, both Inspector Grover and the building board counter-argued that under current state structural laws, any active manufacturing enterprise is strictly required to feature a three-hour rated firewall boundary, regardless of whether its product output is technically classified as a low, moderate, or high hazard. Grover further revealed that although Olympic Adhesives had successfully secured a specialized manufacturing permit for a limited industrial zone from the zoning board, the firm had been blocked from receiving a final occupancy permit due to the unresolved firewall dispute. Board members John Reardon, Ernest Higgins, and Larry Harrold voted unanimously to deny the waiver. Because the state building code had recently been updated to legally supersede all municipal regulations, the board’s local decision was formatted to be sent directly to the state Building Code Commission for final administrative approval.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Norwood Selectmen Approve Infrastructure Improvements for Upland Road-July 12, 1971
Local leaders also enacted emergency measures for the town dump to comply with state sanitary regulations and adjusted the 1971 tax rate through light department fund transfers.

-
Selectmen Approve Upland Road and Clapboardtree Street Infrastructure Project-July 13, 1971
Local leaders also enacted emergency measures for the town dump to comply with state sanitary regulations and adjusted the 1971 tax rate through light department fund transfers.

-
Engineers Estimate $532,000 Cost for University Avenue Extension-September 4, 1970
A four-month overdue engineering study prepared by Boston-based consultants Fay, Spofford & Thorndike Inc. at a cost of $8,000 has placed an estimated price tag of $532,000 on the proposed 2,700-foot extension of University Avenue. The recommended roadway layout will connect the existing portion of University Avenue with Everett Street just before intersecting Route 1,…

-
Norwood Kills Funds For School Addition-June 26, 1969
Voters approve a $1,000 Endean Park drainage compromise and reverse a zoning rule to relocate Carl A. Johnson’s Norwood Cadillac Co. along Route 1.

-
Norwood Voters To Consider Lighting Funds-June 26, 1968
The Finance Commission backs the utility expansion alongside a $163,000 sewer construction article, while the town master plan is deferred.

-
Industrial Commission Welcomes Star Service Hub-June 30, 1967
Following 50 intensive town meetings to resolve department regulations, developers project the new multi-million square foot industrial hub will lower Norwood’s local tax rate.

-
Ask Town Meeting on Industrial Park-September 7, 1966
Representatives of the development firm Cabot, Cabot & Forbes (CC&F) urged the Board of Selectmen last night to place an article before an early October special town meeting to pave the way for major infrastructure development at the Norwood Industrial Park. C. Brooks Dodge, representing CC&F, asked the board to initiate town meeting action and…

-
State Traffic Engineers Investigate Missing Stop Sign Reports in Norwood-August 31, 1966
Local frustration over municipal traffic safety measures came to a head when town officials addressed long-standing delays regarding state approval for stop signs at key intersections. Commenting on the sluggish bureaucratic pace, one local selectman dryly remarked, “It takes an act of God to post a stop sign!” The exasperation stemmed from a nine-month delay…

-
Oldham School Drainage Repairs Scheduled For Completion-June 24, 1964
Corrective Measures Target Long-Standing Controversy At Elementary Site Corrective measures designed to resolve persisting drainage problems at the Oldham Elementary School are scheduled to be completed by the end of this week. The ongoing drainage difficulties at the new school site had been the subject of a long controversy in discussions of the Oldham School…

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.