Despite ongoing construction challenges and labor disputes, the new Junior High South educational complex in Norwood remains on track for its scheduled September opening.
According to School Superintendent Dr. Philip O. Coakley, the “core” of the $4.5 million project—which includes the essential classrooms, administrative offices, and the auditorium—is expected to be fully operational in time for the start of the school year. Charles Worthington, the project’s clerk of the works, and Theodore J. Beaudet, the construction chief, confirmed that progress is sufficient to meet this goal. However, other portions of the facility, specifically the gymnasium, the cafeteria, and the industrial arts area, face a less certain timeline. Dr. Coakley indicated that he has yet to receive a definitive completion date for these auxiliary spaces from the general contractor, Rocheford Construction Co., Inc. of Natick.
The project, which saw its groundbreaking in October 1972 as a replacement for the aging Washington Street Junior High South, has been managed by the architects Korslund, LeNormand & Quann. John J. Egan, chairman of the Permanent Building Construction Committee, noted that while the project has experienced setbacks, it remains “well within the budget” originally established for construction. Addressing the delays, Dr. Coakley cited a previous carpenters’ strike as a primary factor, while Mr. Egan pointed to current labor strikes involving both painters and ironworkers as ongoing hurdles. Additional complications included the necessity of installing coil walls in the gymnasium, which delayed roof progress. Mr. Egan scheduled a follow-up committee meeting for the week of July 08, 1974, to conduct a more in-depth assessment of the construction schedule, which officially maintains a target completion date of September 1.
In addition to construction logistics, the committee is overseeing site improvements, including the installation of a fence along the rear of the school property situated at the corner of Washington and Mylod streets. The placement of this perimeter had been postponed due to revised plans submitted by the school board that incorporated a new running track into the field area. These specifications are currently awaiting final approval from the state School Building Assistance Bureau (SBAB). Furthermore, the committee has been forced to address damage caused by individuals driving vehicles onto the school’s playing fields, a recurring issue that necessitated the fencing plan. As the town nears the opening date, the Permanent Building Construction Committee continues to monitor the site closely to ensure the facility meets the needs of Norwood’s students.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Andrew J. Ciarletta Jr. Appointed Principal of Winslow Elementary School-July 27, 1966
The Norwood School Committee appointed Andrew J. Ciarletta Jr. as principal of Winslow Elementary School, succeeding Alan R. Wonson.

-
Superintendent Coakley Tells PTA Council That $4 Million in New School Construction Is Mandatory-September 10, 1965
Dr. Philip O. Coakley tells the PTA Council that $4 million in new school construction—including a new elementary and junior high—is mandatory to handle over-capacity enrollment.

-
Norwood School Committee Reviews Summer School Program and Proposes Token Fees-September 3, 1965
Following the successful completion of Norwood’s first town-sponsored summer school program—which enrolled approximately 330 local students in remedial coursework—the Norwood School Committee is evaluating future administrative structures, including a proposal to institute a nominal student fee. Superintendent Philip O. Coakley presented a comprehensive report detailing the inaugural summer session, noting that progress reports for every…

-
School Wiring Hazard Suspected at Norwood Junior High-September 3, 1965
Expressing deep concern over aging infrastructure, the Norwood School Committee has called for an immediate investigation into potential electrical wiring hazards at the Norwood Junior High School to determine whether emergency repairs are urgently required. The inquiry was initiated after Superintendent of Schools Philip O. Coakley delivered an alarming report on the condition of the…

-
Norwood Tennis Courts Recreation-July 10, 1965
On July 10, 1965, Norwood officials were actively working to resolve the placement of a proposed six-court tennis facility at the Prescott School. Recreation Superintendent Richard Ready noted that while the specific site remained undecided, he and other town officials were in the process of analyzing a location proposed by the Norwood School Committee. ⠀…

-
Norwood Renews Search For High School Principal-June 25, 1964
Officials plan to evaluate past candidates and request recommendations from Boston area colleges while Vice Principal John Mombouquette prepares for interim leadership.

-
Enrollment Hike Forces Split Classes in Norwood Public Schools-September 5, 1963
Norwood public schools experience an enrollment spike of 416 students, prompting split classes at Cleveland and Callahan schools and sparking a debate over elementary cafeteria capacity.

-
Eleventh-Hour Decision on Oldham School Registration-September 3, 1963
NORWOOD — An eleventh-hour session of the Oldham School Building Committee is being held tonight to make the decisive call on whether the newly constructed school will officially open its doors for student registration tomorrow morning. Final Scramble and Boiler Inspections Workmen labored through the weekend, including a full day on Saturday, trying to wrap…

-
Oldham School Opening Set for Wednesday, New Teacher Appointments-August 30, 1963
As Norwood prepares for the new academic year, the School Committee has announced plans to open the newly constructed John P. Oldham Elementary School next Wednesday, contingent upon final safety inspections of its heating and ventilating systems. While municipal electric light department crews rushed to finish electrical work and boilers were fired for the first…

-
Bios of New Norwood Public School Teachers-August 29, 1963
As the Norwood public school system prepares for the upcoming academic year, officials announced the appointment of 56 new teachers. Biographical profiles for the first 28 incoming educators highlight their educational backgrounds and assignments: High School Appointments Elementary, Junior High, and Special Services Appointments Discover more from Norwood Historical Society Subscribe to get the latest…

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.