Contractors installing a new sprinkler system at Norwood High School assured the Permanent Building Committee last night that construction will be finished by next Friday, keeping the scheduled September 8 opening date on track.
Project Manager Robert Devoe of Boston’s ABC Sprinkler Co. stated that work will be 98 percent complete by Friday and announced he will personally oversee a second shift of workers starting Monday. The reassurance came after Assistant Superintendent James R. Donovan voiced concerns to the school committee on Wednesday night that installation delays might postpone the start of the academic year. Devoe noted that the cafeteria remains the only major area pending completion, after which the system will undergo rigorous pressure testing.
Engineering Friction and Gym Renovations
Committee members and contractors expressed frustration with Francis J. Thompson of HPR Services of New Hampshire, the engineer responsible for calculating the placement of over 800 sprinkler heads. Vice-Chairman Philip C. Swain reported that a minor calculation error by Thompson stalled necessary project approval from the Insurance Service Office (ISO). Committee members noted they had spent three weeks unsuccessfully trying to get Thompson to meet with the ISO, prompting a phone call and message left at his home during the meeting.
In other facility updates, Vincent Carlson—project manager for Korslund, LeNormand & Quann Inc. supervising high school renovations—reported that gym floor sanding is over 50 percent complete and expected to finish by Wednesday, allowing the application of the first of four finish coats and subsequent court line painting. While the gym floor will not be fully ready by the exact opening day of school, the building’s fire alarm system is scheduled for testing today. Carlson added that a temporary indicator panel has been installed at the insistence of the fire department until the permanent factory unit arrives, which will eventually tie in the completed sprinkler system.
Student Registration and Daily School Schedules
The school department announced registration and schedule guidelines for the upcoming 1976–77 academic year:
- New Student Registration: Open for students entering the Norwood school system for the first time at all school administrative offices, Monday through Friday from 9:00 a.m. to noon and 1:00 to 3:00 p.m. Parents must provide birth and immunization certificates.
- School Opening & Screening: All public schools open on September 8. Kindergarten screening runs from September 8 to 14, with kindergarten classes commencing September 15.
- Daily Time Schedules:
- High School & Henry O. Peabody School: 7:45 a.m. to approximately 2:30 p.m.
- North & South Junior High Schools: 7:45 a.m. to 2:20 p.m.
- Elementary Schools: 8:40 a.m. to 2:55 p.m.
- Kindergarten: Morning session from 8:40 to 11:15 a.m.; afternoon session from 12:30 to 2:55 p.m.
- Bus Transportation Eligibility (Minimum Distance Requirements): High school, 2 miles; junior high schools, 1.5 miles; elementary schools, 1.25 miles; kindergarten through grade 3, 1 mile.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
Andy Scafati Recalls 40 Seasons in Athletics Ahead of Norwood Retirement-September 7, 1972

Longtime Norwood High School athletic director Andy Scafati reflects on 40 years in sports and the remarkable expansion of the town’s athletic programs as he prepares to step down.
-
School Board Reverses Vote, Keeps NorWest Woods Pupils at Oldham-August 29, 1972

In a reversal of a previous decision, the School Committee has voted to keep 46 elementary school children from the Nor-West Woods apartment complex at the Oldham School, rescinding a July 5 vote that would have transferred them to the Shattuck School. Superintendent Dr. Philip O. Coakley explained that the committee revoted on the matter…
-
Norwood Sets $38 Tax Rate on Court-Ordered 100% Property Valuation for 1972-August 16, 1972

Announcing a 1972 tax rate of $38 per $1,000 under a court-ordered 100 percent property valuation, Assessor Chairman James J. Drummey concluded a major reassessment by Cole, Layer and Trumble.
-
Norwood Jr. High Offered Land At $9,500 An Acre-September 30, 1971

The Norwood School Committee recommends the Endean area in Walpole as the site for a new junior high school, facing sharp questioning from town meeting members over rising costs and site shifts.
-
Norwood High School Launches Innovative Open Campus Plan for Fall Term-September 8, 1971

Norwood High School opens the fall term by launching an innovative open campus and extended-day program designed by Principal John F. Monbouquette to foster student responsibility.
-
School Committee Seeks $20,000 for Initial Handicapped Access Upgrades at High School-November 19, 1979

Voting 5-0 after meeting with the Permanent Building Construction Committee in November 1979, the Norwood School Committee requested $20,000 at the Dec. 3 Special Town Meeting for baseline ramps and accessible restrooms at Norwood High School.
-
Schools Face Heating Oil Shortage for Upcoming Winter, While Band Camp and Library Art Programs Make Headlines-August 6, 1970

Superintendent Dr. Philip O. Coakley informed the Norwood School Committee that no companies submitted bids to supply 110,000 gallons of No. 5 heating oil for town schools due to quotas, shortages, and environmental regulations.
-
Bells Are Ringin’-July 3, 1970

The Norwood School Committee overhauled its student transportation system and faced an $8,000 wave of structural school vandalism in July 1970
-
Finance Commission Threatens Postponement of $6.1 Million Senior High Addition Without Comprehensive School Housing Plan-November 13, 1969

Fincom Chairman George T. Mahoney demanded unequivocal backing and cost estimates from the Norwood School Committee for the proposed $6.1 million high school addition ahead of the Special Town Meeting.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.