State officials yesterday granted Norwood school authorities permission to delay the start of classes for high school and vocational students by three days, moving their opening date to September 9. Superintendent James R. Savage requested the postponement to provide teachers and administrators adequate time to prepare the recently closed Junior High North, which will temporarily house 950 high school students while a $5 million renovation of the senior high school is underway.
Savage noted that the extra time is necessary for teachers to familiarize themselves with the building, sort instructional materials, and allow custodians to clean facilities and inspect machinery. Junior High North had been closed over a year prior due to declining enrollment. Meanwhile, elementary and junior high classes remain scheduled to begin on September 4, with kindergarten classes commencing on September 9.
Renovation Timeline and Vocational Relocation
While school officials initially hoped to return students to the main high school following Christmas vacation, Savage acknowledged that construction delays might push that timeline back. Project contractor Anchor Construction officials indicated that portions of the renovation may not wrap up until sometime in October at the earliest.
The Henry O. Peabody School—a vocational and technical high school connected to the main building and included in the renovation project—will also begin classes on September 9 at the Willet School, serving its 203 enrolled students. According to Peabody School Director William P. Maher, administrative letters will notify students that parts of the vocational facility may become ready between September 16 and 23, with students temporarily distributed among Willet School, Norwood Junior High in South Norwood, and Junior High North.
Budgetary Impact
School Business Administrator Stephen R. Hemman estimated that the temporary four-month relocation to Junior High North will cost the town roughly $80,000, though he cautioned that the final price tag remains fluid. While a portion of the expenses will be drawn from the school department’s $13.7 million budget, remaining costs will require funding through a special town meeting or emergency fund transfers.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
Bios of New Norwood Public School Teachers-August 29, 1963

As the Norwood public school system prepares for the upcoming academic year, officials announced the appointment of 56 new teachers. Biographical profiles for the first 28 incoming educators highlight their educational backgrounds and assignments: High School Appointments Elementary, Junior High, and Special Services Appointments Discover more from Norwood Historical Society Subscribe to get the latest…
-
Superintendent Coakley Announces Upcoming Student Registration, New Teacher Orientation, and Summer Maintenance Progress-August 22, 1963

Norwood schools set registration dates and orientation schedules while summer maintenance projects wrap up across local buildings ahead of the September 4 opening.
-
Eight-Room Addition to Cleveland School Recommended Over New Construction-August 16, 1963

Voting 3 to 2, the Elementary School Building Committee recommended an eight-room addition to the Cleveland School over building a new facility, setting a joint meeting with Superintendent Philip O. Coakley.
-
School Building Committee Votes to Recommend Addition to Cleveland School-August 16, 1963

By a 3-2 vote, Norwood’s Elementary School Building Committee recommended an eight-room addition to the Cleveland School rather than constructing a new facility on Wilson Street.
-
Oldham School Building Committee Grapples with Defective Tile Work and Construction Delays-August 7, 1963

At a special meeting addressing 22 construction issues, the Oldham School Building Committee and architect George H. Stoner rejected 1,100 square feet of improperly installed exterior tile.⠀
-
Norwood Junior High Aerial View-October 9, 1957

Norwood Junior High Aerial View-This Day In Norwood History-October 9, 1957
-
School Board Studies Hockey Rink For School, New Schools, Sets New Weather Policy-This Day in Norwood History-June 30, 1946

The Norwood School Committee institutes a firm new inclement weather academic policy, launches cost evaluations for a high school hockey rink, and updates educational equipment for the local schools.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.