An Ambitious Vision for Norwood’s

On July 21, 1978, the town of Norwood found itself contemplating a transformative infrastructure proposal that promised to fundamentally alter the local landscape. According to a report in The Patriot Ledger, the local Department of Public Works (DPW) unveiled a comprehensive, massive road resurfacing project estimated to cost $1.9 million. This sweeping initiative sought to address the long-standing issue of deteriorating street conditions, with the proposed scope detailed across 14 pages of a technical report containing over 300 individual line items.

The project was championed by Selectman Walter J. Dempsey, who argued that the town’s traditional approach to maintenance had proven inadequate. Walter J. Dempsey contended that for the previous 40 years, road upkeep had been systematically neglected. He specifically criticized the annual road maintenance budget of $150,000, characterizing it as a “drop in the bucket” and stating, “You’re not even keeping pace.” Walter J. Dempsey firmly believed that a complete resurfacing of the town’s network was both a practical necessity and a politically viable objective, even amidst the era’s prevailing public sentiment against increased government spending.

To mitigate the financial burden on residents, Walter J. Dempsey proposed a strategic five-year plan funded through a bond issue, which would distribute the $1.9 million cost over an extended timeframe. He also suggested that streets already recently improved and currently in good condition would be excluded from the scope of work. By ensuring that every motorist could depart their home onto smooth, high-quality pavement, Walter J. Dempsey hoped to foster town-wide unity and eliminate the “small sectional jealousies” that often arose from prioritized or uneven local maintenance schedules.

The plan faced significant practical and fiscal scrutiny. DPW Supt. Nicholas G. Joseph provided a more immediate outlook, listing 19 specific streets slated for standard resurfacing in 1979 at a projected cost of $169,975. Howard, a finance commissioner, voiced skepticism regarding the feasibility of such a wide-scale project within a single year, flatly stating, “No way you do that in one year.” He further questioned whether the standard annual budget was simply too lean to address the systemic needs of the town’s roadways. Walter J. Dempsey acknowledged that the support of the Finance Commission (FinCom) was essential for the plan’s success, noting that without such institutional backing, the proposal was “hopeless.”

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Oldham School Drainage Repairs Scheduled For Completion-June 24, 1964

    Corrective Measures Target Long-Standing Controversy At Elementary Site Corrective measures designed to resolve persisting drainage problems at the Oldham Elementary School are scheduled to be completed by the end of this week. The ongoing drainage difficulties at the new school site had been the subject of a long controversy in discussions of the Oldham School…

  • Parking Proposals in Norwood-July 31, 1963

    The Patriot Ledger’s July 31, 1963 edition brought forth a plethora of news stories that captivated the residents of Norwood and surrounding areas. Among these was the Parking Commission’s meeting with the Board of Selectmen to discuss proposals for acquiring land for parking purposes. This pivotal discussion took place in an executive session, which raised…

  • Winslow Train Station Abolished, Leading to Construction of Subway Hill-This Day In Norwood History- July 17, 1891

    This Day In Norwood History- July 17, 1891-Winslow Train Station Abolished, Leading to Construction of Subway Hill


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.