Following months of public hearings and negotiations, the Planning Board voted unanimously last night to recommend against constructing a connecting road between Route 1 and Route I-95 at town expense for the proposed Norwood Arena industrial park development.
“Park Place” Industrial Subdivision Plans
Planning Board Chairman Thomas F. Cavanaugh announced the decision after reviewing a status report from Boston engineering firm Metcalf and Eddy Inc., which was hired to study future industrial development on the 220 buildable acres of the Norwood Arena site. Metcalf and Eddy reported that during an August 19 meeting with the state Department of Public Works (DPW), state officials confirmed they would reject any subdivision design that altered the existing cloverleaf interchange at Neponset Street and Route I-95—ruling out two initial connecting road proposals that required cloverleaf modifications.
Consequently, the planning board voted to inform selectmen that the industrial park—named “Park Place” by developer James H. Shane (31-year-old board chairman of Appendagez Inc. and Faded Glory clothing distributors) after the popular board game—should proceed strictly as an internal industrial subdivision. Drawn by Richard Merriken of Norwood Engineering Co., the master plan encompasses just over one mile of roadway built to county standards for Chapter 90 stipulations, should a highway connection ever become viable in the future.
The planning board established a mandatory bank performance bond of $576,000 for the industrial park development. Merriken reported that the project had already secured approval from the Norwood Conservation Commission and anticipated no obstacles from the U.S. Army Corps of Engineers regarding building permits.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Oldham School Drainage Repairs Scheduled For Completion-June 24, 1964

Corrective Measures Target Long-Standing Controversy At Elementary Site Corrective measures designed to resolve persisting drainage problems at the Oldham Elementary School are scheduled to be completed by the end of this week. The ongoing drainage difficulties at the new school site had been the subject of a long controversy in discussions of the Oldham School…
-
Parking Proposals in Norwood-July 31, 1963

The Patriot Ledger’s July 31, 1963 edition brought forth a plethora of news stories that captivated the residents of Norwood and surrounding areas. Among these was the Parking Commission’s meeting with the Board of Selectmen to discuss proposals for acquiring land for parking purposes. This pivotal discussion took place in an executive session, which raised…
-
Winslow Train Station Abolished, Leading to Construction of Subway Hill-This Day In Norwood History- July 17, 1891

This Day In Norwood History- July 17, 1891-Winslow Train Station Abolished, Leading to Construction of Subway Hill
-
The Town Reservoir and Water Towers- 1890

1890- The Commissioners beg to renew the recommendation of a former Board, and strongly urge the town to lay a six-inch main pipe from the corner of Winter and Prospect Sts., to connect with the main pipe on Cottage Street. This connection by continuous pumping will ensure the town a supply of water, in case…
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.