Architect Refuses to Accept 1,100 Square Feet of Exterior Tile at Special Meeting Addressing 22 Construction Issues

Several eleventh-hour construction and administrative hurdles were tackled by the Oldham School Building Committee during a special meeting called last night, headlined by a major dispute over defective masonry. Of prime importance among a list of 22 agenda items was a contentious problem involving the removal of roughly 1,100 square feet of exterior tile. Architect George H. Stoner advised the committee that he formally refused to accept the tile work, characterizing the installation as “poor workmanship.” Stoner explained that the root of the issue stemmed from the wall surface being improperly prepared before the tiles were laid, violating protocol since the tile firm was instructed never to proceed unless the foundation was in acceptable condition.
Prime contractor Edward Goverman Jr. of Canton stated he would be willing to tear down the flawed tiles himself, but noted that a professional tile setter would be required to redo the installation. However, union complications threatened to stall remediation; Goverman warned that because the original subcontractor was unionized, other union personnel currently working on the school might refuse to touch the repair job until all ongoing phases of construction are completed. Architect Stoner warned that the standoff could potentially trigger legal action between the prime contractor and the tile subcontractor, noting that he had requested industry experts to inspect the site. The Building Committee declined to dictate a solution to the contractor, demanding an immediate fix while expressing uncertainty over whether the extensive repairs could be wrapped up before the school’s September opening.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
School Drop-In Centers Possible In Fall-June 24, 1974
Citing summer custodial constraints and a lack of air conditioning, town officials vote to survey local youths during the summer to prepare for a fall launch.

-
Public Schools Face Delays and Possible State Action on Mandatory Hot Lunch Program-August 31, 1973
Parents of elementary school students in Norwood will need to continue packing brown-bag lunches for the start of the academic year. School Superintendent Philip O. Coakley announced that the town will fail to meet the state-mandated September deadline for implementing a universal public school hot lunch program, exposing the municipality to potential legal action by…

-
Norwood High School Refines Open Campus Program in Second Year of Operation-October 2, 1972
Entering its second year, Norwood High School’s open campus system sees tighter corridor rules, sophomore restrictions, and expanded academic seminars while undergoing state-mandated evaluation.

-
Andy Scafati Recalls 40 Seasons in Athletics Ahead of Norwood Retirement-September 7, 1972
Longtime Norwood High School athletic director Andy Scafati reflects on 40 years in sports and the remarkable expansion of the town’s athletic programs as he prepares to step down.

-
School Board Reverses Vote, Keeps NorWest Woods Pupils at Oldham-August 29, 1972
In a reversal of a previous decision, the School Committee has voted to keep 46 elementary school children from the Nor-West Woods apartment complex at the Oldham School, rescinding a July 5 vote that would have transferred them to the Shattuck School. Superintendent Dr. Philip O. Coakley explained that the committee revoted on the matter…

-
Norwood Sets $38 Tax Rate on Court-Ordered 100% Property Valuation for 1972-August 16, 1972
Announcing a 1972 tax rate of $38 per $1,000 under a court-ordered 100 percent property valuation, Assessor Chairman James J. Drummey concluded a major reassessment by Cole, Layer and Trumble.

-
Norwood Jr. High Offered Land At $9,500 An Acre-September 30, 1971
The Norwood School Committee recommends the Endean area in Walpole as the site for a new junior high school, facing sharp questioning from town meeting members over rising costs and site shifts.

-
Norwood High School Launches Innovative Open Campus Plan for Fall Term-September 8, 1971
Norwood High School opens the fall term by launching an innovative open campus and extended-day program designed by Principal John F. Monbouquette to foster student responsibility.

-
Schools Face Heating Oil Shortage for Upcoming Winter, While Band Camp and Library Art Programs Make Headlines-August 6, 1970
Superintendent Dr. Philip O. Coakley informed the Norwood School Committee that no companies submitted bids to supply 110,000 gallons of No. 5 heating oil for town schools due to quotas, shortages, and environmental regulations.

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.