Town Study Committee Backs Civic Center Appraisal-October 19, 1976
Moving one step closer to a definitive decision regarding the future of Norwood Hospital, the town’s hospital study committee recommended last night that selectmen authorize an independent architectural appraisal of the Civic Center property.
Meeting with hospital leadership—including board of trustees president John Fuller, vice president John Draper, and hospital administrator David P. Buchmueller—the committee received formal assurances that the hospital would fully reimburse the town for the appraisal cost (estimated at no more than $1,000) if the hospital trustees ultimately decided against acquiring the Civic Center site, which is located adjacent to the hospital.
Fuller informed the committee that the hospital’s comprehensive health planning committee had already approved expansion plans centered on the Civic Center property and would formally recommend the site to the board of trustees at an upcoming October 27 meeting.
Administrator David P. Buchmueller emphasized the urgency of the timeline, noting that the hospital must file a certificate of need application with the state by January 1. “If we miss that date we’ll have to wait until May 1,” he warned, “and with a $20 million project, costs will be going up all the time.”
Replacement of Recreation Facilities and Proposed Sites-October 19, 1976
The Civic Center location has emerged as the preferred solution for the hospital’s severe space constraints, backed by both municipal leaders and an independent consulting firm hired by the hospital. Under the proposed agreement, the hospital would completely replace the recreation facilities currently housed at the Civic Center on a new town-selected site.
When Rudith Berkowitz questioned whether the hospital would replace the existing small swimming pool with an Olympic-sized pool, Fuller clarified, “The hospital would be paying for replacement of existing facilities, but enhancement of those facilities would be up to the town of Norwood.”
Selectman Walter J. Dempsey proposed an alternative approach: dispersing replacement recreational facilities across town rather than rebuilding them in a single complex—such as constructing a new swimming pool in conjunction with a local school for shared student and community use. While Recreation Director Robert Ivatts favored keeping the entire complex unified, the hospital study committee previously outlined four potential alternative locations on August 16:
- 10 acres at Walpole and Wilson Streets owned by contractor Frank Simoni.
- 6.5 acres behind the Balch School.
- Land behind Junior High School North near the Father McAleer Playground.
- 23 acres adjoining conservation land on Mylod Street, owned by Charles S. Bird.
Expansion Design and Addressing Veterans’ Concerns-October 19, 1976
Detailing the architectural plans, Buchmueller explained that the $20 million project would involve closing off Winter Street from Washington Street to Linden Street, with all floors in the proposed new structure connecting directly to corresponding floors in the existing hospital building. He also noted that acquiring properties on Linden Street would serve long-range space needs, while assuring committee members that the expansion would incorporate at least 500 new parking spaces to permanently resolve area parking shortages.
Discussions also touched on local opposition, as Walter J. Dempsey and Frank Civattone—representing veterans’ organizations on the committee—exchanged sharp words regarding the fact that the Civic Center serves as a veterans’ memorial. Dempsey argued that most town veterans did not belong to organized clubs and felt that veterans’ groups lacked full information regarding the proposal, stating, “I will go before any veterans’ organization and argue this case.”
Next Steps and Public Briefings-October 19, 1976
Selectmen Chairman and study committee head Joseph F. Curran urged the committee to prepare formal presentations for a special town meeting, pending approval by the hospital board. Dempsey was scheduled to present the committee’s appraisal recommendation to the Board of Selectmen, which in turn needed to secure a reserve fund transfer from the Finance Commission.
To ensure complete transparency alongside the hospital’s independent valuation, hospital officials agreed to brief town meeting members directly on Thursday evening regarding detailed design concepts, cost factors, and documentation.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More Norwood Hospital Stories
-
Four Years After Flash Flood, Norwood Hospital Site Sits as Unfinished Shell-September 23, 2024
Four years after a flash flood and amid Steward Health Care’s bankruptcy, Norwood community leaders and lawmakers scramble to find an operator to rebuild and reopen Norwood Hospital.

-
Intersection at Washington & Winter Streets
This intersection has lots going on as far as Norwood History goes. Directly in front of us is the site of Norwood Hospital. Currently, the hospital, which was flooded and damaged in June of 2020, is in the process of being rebuilt with an opening scheduled for spring of 2024. That piece of land was…

-
Winter Street (Walpole St to Lothrop Rich Park)
First Congregational Church. Originally was the site of the impressive house of Edmund Shattuck and his wife Emma Morrill Shattuck who was the daughter of Morrill Ink Works owner George Morrill. Edmund Shattuck managed the Ink Works one of Norwood’s prosperous industries until his death in 1903. At one point in it’s history Morrill Ink…

-
Development of the Guild Square Area
In 1872, when Norwood was established, the Guild Square area had been settled with homes and businesses for well over a hundred years, although much of the area was undeveloped farmland until the mid-1880s. Not too far from here Aaron Guild left his plow in the field, picked up his musket and went to fight…

-
Norwood Hospital Demolition
Below you will find links to all our posts about the demolition at Norwood Hospital. Do you have photos or videos of the demolition work at Norwood Hospital you would like to share? Please send them to us! Include your name and the date they were taken and you will receive credit in the captions.…
-
Norwood Hospital Demolition-The End Is Near For Norwood Hospital
Below you will find links to all our posts about the ongoing demolition at Norwood Hospital. Do you have photos or videos of the demolition work at Norwood Hospital you would like to share? Please send them to us! Include your name and the date they were taken and you will receive credit in the…

-
Norwood Hospital Demolition-Last Of the Draper Building-October 19, 2022
Below you will find links to all our posts about the ongoing demolition at Norwood Hospital. Do you have photos or videos of the demolition work at Norwood Hospital you would like to share? Please send them to us! Include your name and the date they were taken and you will receive credit in the…

-
Norwood Hospital Demolition- Draper Building- October 16, 2022
Below you will find links to all our posts about the ongoing demolition at Norwood Hospital. Do you have photos or videos of the demolition work at Norwood Hospital you would like to share? Please send them to us! Include your name and the date they were taken and you will receive credit in the…