Norwood High School’s $5 million renovation project will not be completed by the time classes are scheduled to resume on September 3, the project contractor informed town officials. Thomas Boyle, owner of Anchor Construction Co. of Lowell, stated during a joint meeting that the facility will not be ready for occupancy until October 15 at the earliest, citing persistent subcontractor issues and late material deliveries.

Major construction work remains incomplete on corridor floors and ceilings, heating and electrical systems, and critical safety infrastructure, including fire alarms and sprinkler systems, though most classroom work is finished. School Superintendent James Savage told the building committee that officials face costly decisions regarding temporary student housing, noting that the strongest alternative is utilizing the vacant Junior High School North. When building committee member Edward McDonough asked Boyle if he would bank on a September 3 opening, Boyle candidly replied, “No, in my opinion, if you can put those kids someplace else, put them someplace else.”

While construction supervisor Daniel Egan noted that 108 workers remain on site, missing key shipments—such as fire doors and heating ventilators—prevent building inspectors from granting occupancy. Committee members and project architect Richard Heydecker, along with high school Principal John Piccirilli and school committee Chairman Richard Kief, reviewed options including early dismissals or partial occupancy. However, Superintendent Savage cautioned that construction noise and uncompleted cafeterias would severely disrupt instruction, while Heydecker warned that environmental controls on the new heating system might remain unstable through January. The school committee scheduled a follow-up meeting to determine final student placement.

(Reporting by Bernie McEvoy, The Patriot Ledger).

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Norwood High School Releases Fourth-Quarter Honor Roll-August 14, 1986

    Norwood High School announced its student honor roll for the fourth quarter of the 1985-1986 academic year, recognizing academic achievement across senior, junior, and sophomore classes.

  • Extra $10,000 Approved for High School Renovation-August 7, 1986

    Amid project delays tied to Anchor Construction Corp., the Norwood Finance Commission voted 3-1 to approve an extra $10,000 for KL&Q Architects to oversee the completion of the $5 million high school renovation.

  • School Opening Delayed for High School Students-August 27, 1985

    Norwood high school classes are delayed to September 9 as students temporarily relocate to Junior High North during a $5 million renovation project.

  • High School Students to Relocate to Vacant Junior High School North-August 21, 1985

    Citing extensive construction delays by Anchor Construction Co., Norwood school officials voted to move nearly 950 high school students to Junior High School North for the start of the school year.

  • Norwood School Officials Weigh Alternatives as Renovation Delays Threaten High School Opening-August 8, 1985

    Norwood school officials discussed seven alternatives for opening day if $5 million high school renovations are not finished, while firmly rejecting double sessions.

  • Norwood Rejects Rockland Offer of Part Payment-July 16, 1985

    The summer of 1985 was a time of great economic uncertainty in Massachusetts, with the state facing significant budget deficits and high unemployment rates. However, amidst this backdrop of fiscal woes, the town of Norwood found itself embroiled in a dispute with its neighboring municipality, Rockland, over tuition fees for vocational school students. The issue…

    Stack of papers listing vocational school costs including tuition, equipment, registration, and book fees
  • Norwood High School Implements Total Smoking Ban-July 3, 1985

    In July 1985, the Norwood School Committee unanimously approved a total smoking ban at Norwood High School to begin in September, prioritizing the health of its students.

    Ashtray filled with cigarette butts labeled 'No Smoking' with people drinking and smoking in background
  • Recess is a Popular Subject Among Crop of First Graders-September 6, 1984

    First-grader Amy Frigulietti sat at her desk yesterday, reaching inside to rearrange her freshly sharpened pencils, pens, and a notebook featuring a picture of Michael Jackson on the cover. Like many of her peers across Norwood, 6-year-old Amy was eager for the new term in teacher Sandy Barner‘s class at Prescott Elementary School, though she…

  • Rain-Damaged Cleveland and Prescott Schools Expected to Be Repaired by September-August 17, 1983

    Unexpected rainstorms caused roof leaks at the Cleveland and Prescott schools during active construction, though officials expect full contractor-funded repairs before the September opening.

  • Norwood Public School Students Score Strongly on State Basic-Skills Exams-September 2, 1982

    Students across Norwood public schools have demonstrated exceptional academic performance, scoring remarkably well on state-mandated basic-skills tests for the second consecutive year. Released recently following examinations administered last spring, the district data reveals that only a very small handful of students across grades three, five, and eight failed to achieve minimum passing standards in reading,…


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.