Reopening Target Set for Mid-November Following Construction Delays
Students attending the Henry O. Peabody vocational school may finally return to their classrooms by mid-November, according to estimates discussed at last night’s permanent building construction committee meeting. While project manager John Sosnowski of Anchor Construction of Lowell—the general contractor handling the $5 million renovation of the high school and the adjacent Peabody facility—maintained the building could be ready by November 8, committee members advised a more conservative timeline.
“Realistically, you’re not looking at anything earlier than Nov. 15, and probably Thanksgiving week,” stated committee member Roger Pelletier. Furthermore, architect Richard Heydecker of Korslund, LeNormand & Quann noted that a final post-construction cleanup will require an additional three to seven days.
The extensive renovation project was originally slated for completion on August 30. Because that deadline was missed, the school department had to scramble to find temporary alternative class spaces for the approximately 175 displaced Peabody students, scattering them between Junior High South and the Willett school—arrangements that both administrators and students have criticized as inadequate.
Permanent Building Committee Withholds $37,000 Over Defective Athletic Fields
In addition to delays at the vocational school, tensions flared regarding the high school renovation project. The construction committee voted to withhold approximately $37,000 in payments to Anchor Construction due to severe dissatisfaction with the newly redesigned football field and running track.
High School Athletic Director Arthur Gulla detailed a litany of complaints, pointing out that the field lacks proper grading and the necessary dome-topped curvature required for adequate drainage and turf protection, resulting in poor sod growth. Gulla warned that correcting the issues will cost two growing seasons. In the meantime, the school department is absorbing a $4,500 annual transportation expense to bus football players to Junior High South for practices, while playing all games entirely away from home.
“We’re spending $4,500 to transport kids to practice, and we probably will next year too,” Gulla said. “We’re playing all our games away—it’s not fair to the kids.” While Sosnowski defended the grading as correct, he agreed that a professional surveyor will evaluate the field the following week to determine whether regrading is necessary.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974

After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.
-
Unfinished Junior High To Open On Schedule-July 8, 1974

Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.
-
School Board Rejects ‘Floating Principal’ Proposal-July 03, 1974

The Norwood School Committee held a contentious session on the evening of July 2, 1974, where, following two weeks of deliberation and a lengthy 90-minute executive session, the board voted 5-1 to reject a proposal to create a new administrative position titled “floating principal.“ The concept, initially championed by Committee Member Joseph M. Pentowski, was…
-
School Drop-In Centers Possible In Fall-June 24, 1974

Citing summer custodial constraints and a lack of air conditioning, town officials vote to survey local youths during the summer to prepare for a fall launch.
-
School Committee Unanimously Approves Period of Silent Meditation Following State Legislative Act-October 25, 1973

Acting on a new state law permitting voluntary reflection, the Norwood School Committee unanimously approved a daily period of silent meditation for local students and teachers.
-
Proposal Would Combine High School and Henry O. Peabody School Facilities-October 4, 1973

The School Committee reviews a preliminary proposal to combine Norwood High School and Henry O. Peabody School facilities for a new career development and vocational program.
-
Public Schools Face Delays and Possible State Action on Mandatory Hot Lunch Program-August 31, 1973

Parents of elementary school students in Norwood will need to continue packing brown-bag lunches for the start of the academic year. School Superintendent Philip O. Coakley announced that the town will fail to meet the state-mandated September deadline for implementing a universal public school hot lunch program, exposing the municipality to potential legal action by…
-
Norwood High School Refines Open Campus Program in Second Year of Operation-October 2, 1972

Entering its second year, Norwood High School’s open campus system sees tighter corridor rules, sophomore restrictions, and expanded academic seminars while undergoing state-mandated evaluation.
-
Andy Scafati Recalls 40 Seasons in Athletics Ahead of Norwood Retirement-September 7, 1972

Longtime Norwood High School athletic director Andy Scafati reflects on 40 years in sports and the remarkable expansion of the town’s athletic programs as he prepares to step down.
-
School Board Reverses Vote, Keeps NorWest Woods Pupils at Oldham-August 29, 1972

In a reversal of a previous decision, the School Committee has voted to keep 46 elementary school children from the Nor-West Woods apartment complex at the Oldham School, rescinding a July 5 vote that would have transferred them to the Shattuck School. Superintendent Dr. Philip O. Coakley explained that the committee revoted on the matter…
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.