A four-month overdue engineering study prepared by Boston-based consultants Fay, Spofford & Thorndike Inc. at a cost of $8,000 has placed an estimated price tag of $532,000 on the proposed 2,700-foot extension of University Avenue.

The recommended roadway layout will connect the existing portion of University Avenue with Everett Street just before intersecting Route 1, effectively eliminating American Drive as the current continuation of University Avenue. Consultants noted that the extension will cut through the edge of the town’s Ellis Well Field, prompting recommendations to abandon a large gravel-wall well and several smaller wells. Though the field served as a primary municipal water source prior to tying into the Metropolitan District Commission (MDC) water system in 1957—and now serves only emergency needs—engineers suggested conducting formal pumping tests and cost analyses before making a final abandonment decision.

Traffic Projections and Funding Structure

The study projects that traffic volume utilizing the completed extension will necessitate a four-lane, 12-foot-wide configuration—double the width of a standard Chapter 90 county road. The roadway is designed to serve as an industrial bypass for the Route 1-Route 128 interchange, accommodating motorists coming from the nearby Polaroid Corp. plant while providing direct access to Route 128, Route I-95, and Route 1 to increase regional industrial property values.

Regarding construction timelines and financing, developers Cabot, Stride & Forbes Inc. preferred delaying completion until surrounding industrial parcels were fully developed. However, municipal officials anticipate securing state and county financial backing under Chapter 90, wherein the state covers 50 percent of construction costs while the county and town split the remaining balance evenly. Consultants cautioned that construction must be completed within two years to remain eligible for Chapter 90 assistance, pointing out that a connecting stretch of University Avenue in Westwood spanning from Blue Hill Drive to Canton Street has historically never been accepted as a town street.

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Norwood Selectmen Delay Walpole Sewer Tie-In Amid Flooding Concerns and Scrutinize Police Logs-August 2, 1972

    The Norwood Board of Selectmen delayed a proposed Walpole sewer tie-in agreement over flooding concerns, while Selectman William F. Butters clashed with Police Chief James M. Murphy over police logs.

  • Norwood Selectmen Approve Infrastructure Improvements for Upland Road-July 12, 1971

    Local leaders also enacted emergency measures for the town dump to comply with state sanitary regulations and adjusted the 1971 tax rate through light department fund transfers.

  • Selectmen Approve Upland Road and Clapboardtree Street Infrastructure Project-July 13, 1971

    Local leaders also enacted emergency measures for the town dump to comply with state sanitary regulations and adjusted the 1971 tax rate through light department fund transfers.

  • Engineers Estimate $532,000 Cost for University Avenue Extension-September 4, 1970

    A four-month overdue engineering study prepared by Boston-based consultants Fay, Spofford & Thorndike Inc. at a cost of $8,000 has placed an estimated price tag of $532,000 on the proposed 2,700-foot extension of University Avenue. The recommended roadway layout will connect the existing portion of University Avenue with Everett Street just before intersecting Route 1,…

  • Norwood Kills Funds For School Addition-June 26, 1969

    Voters approve a $1,000 Endean Park drainage compromise and reverse a zoning rule to relocate Carl A. Johnson’s Norwood Cadillac Co. along Route 1.

    Open ledger titled County Ledger 1969 with budget requests marked 'Budget Cut' and a judge's gavel on a wooden desk
  • Norwood Voters To Consider Lighting Funds-June 26, 1968

    The Finance Commission backs the utility expansion alongside a $163,000 sewer construction article, while the town master plan is deferred.

    Series of tall metal power transmission towers with electrical wires over fields and hills
  • Industrial Commission Welcomes Star Service Hub-June 30, 1967

    Following 50 intensive town meetings to resolve department regulations, developers project the new multi-million square foot industrial hub will lower Norwood’s local tax rate.

  • Ask Town Meeting on Industrial Park-September 7, 1966

    Representatives of the development firm Cabot, Cabot & Forbes (CC&F) urged the Board of Selectmen last night to place an article before an early October special town meeting to pave the way for major infrastructure development at the Norwood Industrial Park. C. Brooks Dodge, representing CC&F, asked the board to initiate town meeting action and…

  • State Traffic Engineers Investigate Missing Stop Sign Reports in Norwood-August 31, 1966

    Local frustration over municipal traffic safety measures came to a head when town officials addressed long-standing delays regarding state approval for stop signs at key intersections. Commenting on the sluggish bureaucratic pace, one local selectman dryly remarked, “It takes an act of God to post a stop sign!” The exasperation stemmed from a nine-month delay…

  • Selectmen Call for Up-to-Date Delinquent Debt Listing-August 26, 1965

    Norwood selectmen called for updated listings of delinquent town service accounts and authorized Dr. Norton Fishman to construct an access road along George Willett Parkway at his own expense.


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.