A four-month overdue engineering study prepared by Boston-based consultants Fay, Spofford & Thorndike Inc. at a cost of $8,000 has placed an estimated price tag of $532,000 on the proposed 2,700-foot extension of University Avenue.
The recommended roadway layout will connect the existing portion of University Avenue with Everett Street just before intersecting Route 1, effectively eliminating American Drive as the current continuation of University Avenue. Consultants noted that the extension will cut through the edge of the town’s Ellis Well Field, prompting recommendations to abandon a large gravel-wall well and several smaller wells. Though the field served as a primary municipal water source prior to tying into the Metropolitan District Commission (MDC) water system in 1957—and now serves only emergency needs—engineers suggested conducting formal pumping tests and cost analyses before making a final abandonment decision.
Traffic Projections and Funding Structure
The study projects that traffic volume utilizing the completed extension will necessitate a four-lane, 12-foot-wide configuration—double the width of a standard Chapter 90 county road. The roadway is designed to serve as an industrial bypass for the Route 1-Route 128 interchange, accommodating motorists coming from the nearby Polaroid Corp. plant while providing direct access to Route 128, Route I-95, and Route 1 to increase regional industrial property values.
Regarding construction timelines and financing, developers Cabot, Stride & Forbes Inc. preferred delaying completion until surrounding industrial parcels were fully developed. However, municipal officials anticipate securing state and county financial backing under Chapter 90, wherein the state covers 50 percent of construction costs while the county and town split the remaining balance evenly. Consultants cautioned that construction must be completed within two years to remain eligible for Chapter 90 assistance, pointing out that a connecting stretch of University Avenue in Westwood spanning from Blue Hill Drive to Canton Street has historically never been accepted as a town street.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Guild School Picked for Civic Center-July 8, 1980
Discover the 1980 decision that transformed the Aaron Guild School into a multi-purpose recreation hub, replacing the former Civic Center sold to Norwood Hospital.

-
Only Two Norwood Intersections Qualify for Right Turns on Red Under New State Law-October 3, 1979
Following a town survey, Town Manager John J. Carroll announces that right-on-red turns will be permitted at only two Norwood intersections when the state law takes effect.

-
Norwood Selectmen Consider One-Way Traffic, Business District Upgrades-August 8, 1979
Building on the Washington Street revitalization project, Town Manager John J. Carroll proposed working with local merchants to secure a second Urban Systems grant for Nahatan Street improvements.

-
Road Resurfacing Project in Norwood-This Day In Norwood History-July 21, 1978
Faced with decades of neglected road maintenance, Norwood officials debated an ambitious $1.9 million resurfacing plan in 1978. While proponents saw it as a path to smooth roads, others questioned the feasibility of the massive effort.

-
Uncertainty Looms Over Norwood Junior High South Opening Date-July 12, 1974
After three years of double sessions following a 1971 fire, Norwood officials faced the possibility of further delays for the new Junior High South.

-
Unfinished Junior High To Open On Schedule-July 8, 1974
Discover the construction history of the $4.5 million Junior High South project in 1974, detailing the challenges faced during the transition from the old Washington Street school.

-
Selectmen Authorize Water Main Connection and Space Transfers for Phased-Out Schools-June 26, 1974
Shaw Street Infrastructure Upgrades Approved While Winslow and Shattuck Buildings Repurposed for Town Services The Board of Selectmen enacted a series of municipal infrastructure and real estate management decisions during last night’s executive session. In a unanimous vote, selectmen approved a formal request to seek a $16,000 budget transfer from the Finance Commission to construct…

-
Alandale Parkway Residents Demand Answers on Long-Delayed Street Acceptance-September 13, 1972
Alandale Parkway residents demand answers from Norwood selectmen regarding a decade-long delay in street acceptance and severe sidewalk deterioration.

-
$1.8 Million in Major Traffic and Safety Improvements Recommended-September 1, 1972
Comprehensive Traffic and Safety Overhaul Recommended for Norwood in Final Federal TOPICS Report A comprehensive and exhaustive final engineering report, recently delivered to local town selectmen, has outlined a sweeping, multi-faceted proposal to dramatically overhaul Norwood’s municipal road network, upgrade intersection safety, and alleviate escalating vehicular congestion throughout the community. Prepared by the prominent Chestnut…

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.