Fencing, repaving, and minor drainage corrections which are now under way, will complete the commitment of the permanent building construction committee to Norwood Junior High North, according to chairman Richard W. Kief. The school was opened to students in January and officially dedicated last month.
Mr. Kief said a 6 foot chain link fence will be constructed along the Vernon, Irving and Prospect Street boundaries of the school property and bids are now out for this project. He also said some repaving is necessary to widen the bus turn-around in front of the school. Residents of Irving Street have complained recently to both the building committee and the school committee about buses using their street to enter school grounds and have recommended that the Prospect Street driveway be used for both entrance and exit by means of a loop in front of the school. However, Mr. Kief said that any decision in this regard would have to be made by the school department.
The building committee also received a report from Arthur D. Little, Inc. stating that a survey of Norwood’s school building needs is about three-quarters completed. Mr. Kief said the report was “quite general” and did not specify a completion date, although the finance commission reported last week that they expect a written report by the third week of June.
The $42,000 independent survey was substituted for a $6.1 million high school addition by a November 1969 town meeting, because of town officials disagreement over school building priorities. The 10-year master plan for school facilities, buildings and grounds, will allow for planned growth of schools, efficient use of facilitites, budgeting, educational specifications planning, design development and bid timing, according to the firm’s representatives.
The Patriot Ledger, May 29, 1970
Text and images may have been created, edited, colorized, or digitally restored using AI tools such as Microsoft Copilot or Google Gemini. All content is reviewed for accuracy and historical integrity before publication by the Norwood Historical Society
More School Stories
-
Norwood Ousts 3 Who Fought School Budget Cut-September 7, 1978
Three Norwood School Committee members who refused to agree to a $600,000 budget cut were voted out of office in a recall election Tuesday. The election, the second in Norwood this century, came just one day before schools opened, but officials said the opening of the town’s 12 schools went smoothly. The election was the…

-
Auditorium Crowd Supports School Budget-June 8, 1978
A packed hearing at the Aaron Guild School turns into an arena of support for public education as town officials dispute FinCom’s budget metrics.

-
Henry O. Peabody School Graduates 130-June 18, 1977
Dr. Gerard Saunders Delivers Keynote Address Offering Six Practical Guidelines For Entering Working World “The time has come to prove yourselves,” said Dr. Gerard Saunders, guest speaker at the Awards Day Program of the Henry O. Peabody School yesterday. Addressing the 130 graduating students, Dr. Saunders, a professor of law at Mass. Bay Community College,…

-
School Board Confronts Stalled Teacher Negotiations and Implements Stricter High School Credit Policies-June 20, 1974
From 1912 chair distributions to honoring a World War II veteran patrolman, the school board settles wide dockets.

-
High School Addition Plan Okayed-June 20, 1974
Principal Monbouquette details structural upgrades and media center conversions to combat overcrowding.

-
Saraca Criticizes Band Appearance-June 19, 1974
A dispute erupts over an “eleventh-hour decision” to allow a student band performance for fundraising.

-
School Committee Split Over Closing the Shattuck and Winslow Buildings-June 19, 1974
Debate intensifies at a Norwood School Committee meeting over redistricting, school closures, and federal grants.

-
School Committee Reverses Votes-June 3, 1971
In 1970, the Norwood School Committee reversed two earlier decisions after strong parent turnout, restoring Shattuck School students to Junior High North and adopting a mid‑year “flip‑flop” double‑session schedule while addressing civic center polling and a hospital parking dispute.

-
Officials Weighing School Repair Cost-March 6, 1971
Selectmen last night favored start on work to secure walls of the fire-gutted third story of Norwood Junior High School South which are still standing after a section of the rear wall collapsed Thursday. Architect’s Proposal The local architectural firm of Korslund, LeNormand and Quann, Inc., which directed the construction of the temporary roof damaged…