Despite ongoing construction challenges and labor disputes, the new Junior High South educational complex in Norwood remains on track for its scheduled September opening.
According to School Superintendent Dr. Philip O. Coakley, the “core” of the $4.5 million project—which includes the essential classrooms, administrative offices, and the auditorium—is expected to be fully operational in time for the start of the school year. Charles Worthington, the project’s clerk of the works, and Theodore J. Beaudet, the construction chief, confirmed that progress is sufficient to meet this goal. However, other portions of the facility, specifically the gymnasium, the cafeteria, and the industrial arts area, face a less certain timeline. Dr. Coakley indicated that he has yet to receive a definitive completion date for these auxiliary spaces from the general contractor, Rocheford Construction Co., Inc. of Natick.
The project, which saw its groundbreaking in October 1972 as a replacement for the aging Washington Street Junior High South, has been managed by the architects Korslund, LeNormand & Quann. John J. Egan, chairman of the Permanent Building Construction Committee, noted that while the project has experienced setbacks, it remains “well within the budget” originally established for construction. Addressing the delays, Dr. Coakley cited a previous carpenters’ strike as a primary factor, while Mr. Egan pointed to current labor strikes involving both painters and ironworkers as ongoing hurdles. Additional complications included the necessity of installing coil walls in the gymnasium, which delayed roof progress. Mr. Egan scheduled a follow-up committee meeting for the week of July 08, 1974, to conduct a more in-depth assessment of the construction schedule, which officially maintains a target completion date of September 1.
In addition to construction logistics, the committee is overseeing site improvements, including the installation of a fence along the rear of the school property situated at the corner of Washington and Mylod streets. The placement of this perimeter had been postponed due to revised plans submitted by the school board that incorporated a new running track into the field area. These specifications are currently awaiting final approval from the state School Building Assistance Bureau (SBAB). Furthermore, the committee has been forced to address damage caused by individuals driving vehicles onto the school’s playing fields, a recurring issue that necessitated the fencing plan. As the town nears the opening date, the Permanent Building Construction Committee continues to monitor the site closely to ensure the facility meets the needs of Norwood’s students.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
Norwood to Sue Blue Hills School to Block Budget-July 19, 1990

The town of Norwood was on a collision course with the Blue Hills Regional Technical School in July 1990, as officials prepared to file a lawsuit to block the school’s revised budget for the upcoming academic year. The dispute had been brewing for several weeks, ever since the four district towns – Norwood, Holbrook, Dedham,…
-
Oldham School Portable Classroom Nears Completion-October 12, 1989

Norwood’s Oldham School prepares to open a long-awaited portable classroom by month’s end, and veteran teacher Thomas MacDonough recounts his educational fellowship in West Germany.
-
Newcomers Learn to Take Middle School in Their Stride-September 7, 1989

Transitioning from elementary school to middle school can be an intimidating milestone for any young student, but as classes officially got underway this week, Norwood’s newest middle schoolers quickly learned to take the change in stride. Navigating larger hallways, adjusting to rotating class schedules, and meeting new teachers mark a major rite of passage for…
-
First Day of School Brings Excitement and New Beginnings for Norwood’s Class of 1999-September 10, 1987

Norwood students return to class for the 1987-88 school year, marking the first day of school for the Balch Elementary first-graders who make up the graduating class of 1999.
-
Balch and Norwood High Welcome Students on the First Day of School for the Class of 1999-September 10, 1987

Balch Elementary and Norwood High welcome students back for the 1987-88 academic year, marking the first day of school for the graduating Class of 1999.
-
Norwood High Teachers to Implement Uniform Curriculum Guides Starting Next Week-September 3, 1987

When classes resume next week, high school teachers across Norwood will officially be “going by the book.” Superintendent of Schools James Savage informed the school committee that faculty members teaching every course—from woodshop to algebra—will be required to follow newly established, standardized curriculum guides authored by Norwood educators. Closing the Gap in District Education The…
-
$16,600 Grant Equips New Norwood High School Cable Television Studio-August 18, 1987

Norwood Community Television awarded a $16,600 grant to equip a new student-run television studio at Norwood High School, expanding local cable programming and production training.
-
Norwood High School Releases Fourth-Quarter Honor Roll-August 14, 1986

Norwood High School announced its student honor roll for the fourth quarter of the 1985-1986 academic year, recognizing academic achievement across senior, junior, and sophomore classes.
-
School Opening Delayed for High School Students-August 27, 1985

Norwood high school classes are delayed to September 9 as students temporarily relocate to Junior High North during a $5 million renovation project.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.