Representatives of the Lanning Corp. of Michigan met for a second time last night with members of the Traphole Brook Protection Association to review revised site plans for a proposed shopping center at the crucial junction of Union Street and Route 1 in Norwood.
Developer Consultation and Floodplain Concerns
The collaborative evening session also drew members of the Walpole Conservation Commission and local residents. Association officers publicly commended the corporation for its high level of cooperation in working alongside citizen groups to refine the complex’s design. However, members pushed back against specific engineering proposals intended to mitigate local flooding risks.
Robert Foster, secretary of the Traphole Brook Association, characterized the developer’s proposal to construct two dry retention basins to handle stormwater runoff as a purely “engineering solution.” Foster suggested instead that Lanning Corp. give serious consideration to an alternative plan that would restore the portion of the development bordering Traphole Brook to its original natural state.
The natural watercourse runs directly through a portion of the Lanning property, with significant acreage situated within the designated flood plain. Association President David Bird pointed out that this fragile ecological zone had previously been encroached upon through unauthorized filling allegedly conducted by the property’s former owner, Zoppo Realty Trust of Norwood. Bird noted that although legal action had been initiated against Zoppo, a court injunction halting filling operations was subsequently lifted after state authorities were reportedly informed that the practice had ceased, leaving ongoing litigation “in limbo.”
While stating he did not realistically expect Lanning Corp. to entirely restore the property to its untouched colonial condition, Bird emphasized that the association would be satisfied with substantial environmental improvements carried out collaboratively.
Engineering Solutions and Conservation Direction
Responding to environmental concerns, the corporation’s project engineer outlined the mechanics of the proposed water retention system:
- Rear Retention Basin: Designed primarily to capture and manage stormwater runoff generated across the extensive parking lot and commercial roof surfaces.
- Union Street Basin: Positioned on the corner of Union Street specifically to mitigate overflow flooding from Traphole Brook.
Furthermore, the engineer assured attendees that specialized filtration precautions would be incorporated to prevent urban pollutants from entering the retention basins and eventually draining into the brook. He maintained that the engineering design possessed sufficient storage capacity to safely manage water volumes produced by a catastrophic 100-year recurrence interval storm.
Lanning representatives expressed a continued willingness to cooperate closely with the association on site planning, though the corporate engineer noted that official regulatory direction and final approval must ultimately originate from the Norwood Conservation Commission.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
National Guard Cleans Abandoned Cars Out of Neponset River in Norwood-August 8, 1994

Teaming up with the Canton Rotary Club’s Adopt-A-Stream Program, a 10-member National Guard engineering unit used heavy equipment and chainsaws to pull six rusted vehicles out of the Neponset River off Route 1.
-
Norwood Selectmen Meet on Bird Land Purchase-July 14, 1988

On July 14, 1988, Norwood’s long‑term effort to acquire nearly 300 acres of open space reached a critical moment as selectmen convened an emergency evening meeting at town hall. The immediate focus was the proposed purchase of the 23‑acre Bird farm property off Mylod Street — land considered essential to expanding and protecting the town’s…
-
Norwood Conservation Commission Approves Father McAleer Playground Soccer Fields-July 17, 1985

With $110,000 in Town Meeting funding secured, the Recreation Department plans to complete the project within a year while creating new wetlands.
-
Conservation Commission Approves Proposed Auto Body Shop Near Hawes Brook-August 22, 1979

Despite angry protests from South Norwood residents over flooding and pollution risks near Hawes Brook, the Conservation Commission approved strict environmental conditions for a new auto body shop.
-
Conservation Commission Faces Angry Residents Over Proposed Washington Street Auto Body Shop-August 8, 1979

Amid fierce opposition from South Norwood homeowners concerned over Hawes Brook flooding and pollution hazards, the Norwood Conservation Commission reviewed safety plans for a proposed auto body shop on Washington Street.
-
Charles Strumski Retains Norwood Conservation Seat-August 17, 1977

Despite being denied reappointment by the town manager, veteran official Charles Strumski continues to serve the Norwood Conservation Commission.
-
Norwood Conservation Commission Approves Park Place Industrial Site-August 17, 1977

Developer James H. Shane and the Norwood Conservation Commission have agreed on a 56,000 cubic yard flood mitigation plan for Park Place on Route 1.
-
Conservation Commission Reaches Flood Control Agreement with Park Place Developer-August 17, 1977

Reaching a compromise under the Wetlands Protection Act, Norwood’s conservation commission approved flood control plans for the Park Place industrial park on Route 1.
-
Route 1 Wildlife Sanctuary Established by Owner Andrew Simoni to Protect Local Fauna-August 25, 1975

For 15 years, property owner Andrew Simoni has maintained a private 32-acre wildlife sanctuary along Route 1 in Norwood to protect local animals from hunters.
-
Norwood Conservation Commission Seeks Expert Associates-July 31, 1975

The Norwood Conservation Commission, led by Chairman Bettina Cottrell, launched a community search for scientific and legal associates to assist with open space and wetlands management.