Superintendent Warns Of Possible Double-Session Classes If Washington Street Facility Openings Fail

A construction site for North Junior High with a blueprint of the school's first and ground floor, a safety sign, a coffee mug, and construction materials in the foreground.

A steel strike at the end of last summer halted installation of metal decking for the roof and delayed the roofer. Snow and freezing weather further hampered the project before the roof could be completed at the new school site. Without a roof, heat could not be installed and tradesmen could not work inside the building. On May 1, a carpenters strike lasting about six weeks further upset the building schedule.

Richard Burns, building foreman for the project, said yesterday he is still hoping to finish the classrooms and the administrative offices by September. He said the gymnasium and the auditorium would be completed later. School Supt. Philip O. Coakley says he will know for sure whether the school will be ready or not by the end of this week.

He adds that school department officials are studying alternative plans which may be put into effect if the new school does not open on time. James R. Donovan, assistant superintendent for secondary education, says the school department is “still hoping” the school will be ready in September. The school committee will adopt a plan – possibly double sessions – if the junior high is not completed on time. Chairman Saraca says double sessions at the present junior high on Washington Street is a possible solution to the problem that would be created by a delay in opening the North Junior High. The superintendent will present the alternative after more study.

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More School Stories

  • Planning Board Has Done Excellent Work-This Day In Norwood History-May 19, 1923

    Norwood’s Planning Board Unveils an Ambitious Vision for a “Town Beautiful” In the spring of 1923, Norwood residents were invited to look toward the future with the release of the most comprehensive Planning Board report the town had ever produced. The document celebrated more than a decade of civic improvement and laid out an ambitious…

  • New Balch School Ready-This Day in Norwood History-September 2, 1913

    SCHOOLS OF NORWOOD. New Balch Building to Open Tomorrow—Assignment of 12 New Teachers in Various Districts. NORWOOD, Sept 2—The public schools of Norwood open next Wednesday for the Fall term. This date is earlier than usual in this town. The work on the new Balch School Building has proceeded so far that the building is…

    Balch School
  • Norwood Schools To Open Sept 6 With Large Increase in Pupils and Many Changes-This Day in Norwood History- August 21, 1911

    Many Changes Made in Norwood Teaching Force Supt of Schools Austin H. Frittz has announced that the schools of Norwood will open for the fall term Wednesday, Sept 6. It is expected that the attendance on the opening day will be the largest in the history of the town. To accommodate the anticipated increase in…

  • Norwood Sunday Schools Thoroughly Organized-This Day in Norwood History-September 12, 1910

      EVERY CHILD IN SUNDAY SCHOOL. Town of 8000 Well Supplied With Church Buildings. New Ones Completed, and Two Under Way. Mon, Sep 12, 1910 – 16 · The Boston Globe (Boston, Massachusetts) NORWOOD, Sept 12—There is not one child in the large town of Norwood who does not have a Sunday school connection. That…

    Grace Episcopal Church
  • Frank B. Boyden Not Compelled to Send Son to Public School-This Day In Norwood History-January 17, 1910

    DECIDES FOR FATHER. Action Brought by Norwood Committee Against Frank B. Boyden. Can the Norwood School committee compel Frank E. Boyden, the 12-year-old son of Frank B. Boyden of Pleasant st, to attend school, and if it can, should it oblige Mr. and Mrs. Boyden to send the boy to the public schools, was left…

  • New Eight-Room Schoolhouse, Fire Station, Ordered-This Day In Norwood History-November 2, 1905

    New Eight-Room Schoolhouse, Fire Station, Ordered This Day In Norwood History-November 2, 1905

    Winslow School
  • Committee On Public Schools Organized-This Day In Norwood History-August 18, 1905

    This Day In Norwood History-August 18, 1905-Committee On Public Schools Organized

  • High School Will Have Twenty-five Graduates-This Day in Norwood History-June 3, 1904

    June 3, 1904-What is probably die largest class in the school’s history will be graduated at this year’s annual commencement which will occur on the evening of June 16. There will be twenty-five graduates, perhaps……

  • New Norwood Teachers-This Day In Norwood History-August 28, 1903

    This Day In Norwood History-August 28, 1903-New Norwood Teachers

  • The New North Schoolhouse-This Day In Norwood History-August 14,1903

    This Day In Norwood History-August 14,1903-The New North Schoolhouse


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.