State officials yesterday granted Norwood school authorities permission to delay the start of classes for high school and vocational students by three days, moving their opening date to September 9. Superintendent James R. Savage requested the postponement to provide teachers and administrators adequate time to prepare the recently closed Junior High North, which will temporarily house 950 high school students while a $5 million renovation of the senior high school is underway.
Savage noted that the extra time is necessary for teachers to familiarize themselves with the building, sort instructional materials, and allow custodians to clean facilities and inspect machinery. Junior High North had been closed over a year prior due to declining enrollment. Meanwhile, elementary and junior high classes remain scheduled to begin on September 4, with kindergarten classes commencing on September 9.
Renovation Timeline and Vocational Relocation
While school officials initially hoped to return students to the main high school following Christmas vacation, Savage acknowledged that construction delays might push that timeline back. Project contractor Anchor Construction officials indicated that portions of the renovation may not wrap up until sometime in October at the earliest.
The Henry O. Peabody School—a vocational and technical high school connected to the main building and included in the renovation project—will also begin classes on September 9 at the Willet School, serving its 203 enrolled students. According to Peabody School Director William P. Maher, administrative letters will notify students that parts of the vocational facility may become ready between September 16 and 23, with students temporarily distributed among Willet School, Norwood Junior High in South Norwood, and Junior High North.
Budgetary Impact
School Business Administrator Stephen R. Hemman estimated that the temporary four-month relocation to Junior High North will cost the town roughly $80,000, though he cautioned that the final price tag remains fluid. While a portion of the expenses will be drawn from the school department’s $13.7 million budget, remaining costs will require funding through a special town meeting or emergency fund transfers.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
School Drop-In Centers Possible In Fall-June 24, 1974
Citing summer custodial constraints and a lack of air conditioning, town officials vote to survey local youths during the summer to prepare for a fall launch.

-
Public Schools Face Delays and Possible State Action on Mandatory Hot Lunch Program-August 31, 1973
Parents of elementary school students in Norwood will need to continue packing brown-bag lunches for the start of the academic year. School Superintendent Philip O. Coakley announced that the town will fail to meet the state-mandated September deadline for implementing a universal public school hot lunch program, exposing the municipality to potential legal action by…

-
Andy Scafati Recalls 40 Seasons in Athletics Ahead of Norwood Retirement-September 7, 1972
Longtime Norwood High School athletic director Andy Scafati reflects on 40 years in sports and the remarkable expansion of the town’s athletic programs as he prepares to step down.

-
School Board Reverses Vote, Keeps NorWest Woods Pupils at Oldham-August 29, 1972
In a reversal of a previous decision, the School Committee has voted to keep 46 elementary school children from the Nor-West Woods apartment complex at the Oldham School, rescinding a July 5 vote that would have transferred them to the Shattuck School. Superintendent Dr. Philip O. Coakley explained that the committee revoted on the matter…

-
Norwood Sets $38 Tax Rate on Court-Ordered 100% Property Valuation for 1972-August 16, 1972
Announcing a 1972 tax rate of $38 per $1,000 under a court-ordered 100 percent property valuation, Assessor Chairman James J. Drummey concluded a major reassessment by Cole, Layer and Trumble.

-
Norwood Jr. High Offered Land At $9,500 An Acre-September 30, 1971
The Norwood School Committee recommends the Endean area in Walpole as the site for a new junior high school, facing sharp questioning from town meeting members over rising costs and site shifts.

-
Norwood High School Launches Innovative Open Campus Plan for Fall Term-September 8, 1971
Norwood High School opens the fall term by launching an innovative open campus and extended-day program designed by Principal John F. Monbouquette to foster student responsibility.

-
Schools Face Heating Oil Shortage for Upcoming Winter, While Band Camp and Library Art Programs Make Headlines-August 6, 1970
Superintendent Dr. Philip O. Coakley informed the Norwood School Committee that no companies submitted bids to supply 110,000 gallons of No. 5 heating oil for town schools due to quotas, shortages, and environmental regulations.

-
Bells Are Ringin’-July 3, 1970
The Norwood School Committee overhauled its student transportation system and faced an $8,000 wave of structural school vandalism in July 1970

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.