State officials yesterday granted Norwood school authorities permission to delay the start of classes for high school and vocational students by three days, moving their opening date to September 9. Superintendent James R. Savage requested the postponement to provide teachers and administrators adequate time to prepare the recently closed Junior High North, which will temporarily house 950 high school students while a $5 million renovation of the senior high school is underway.

Savage noted that the extra time is necessary for teachers to familiarize themselves with the building, sort instructional materials, and allow custodians to clean facilities and inspect machinery. Junior High North had been closed over a year prior due to declining enrollment. Meanwhile, elementary and junior high classes remain scheduled to begin on September 4, with kindergarten classes commencing on September 9.

Renovation Timeline and Vocational Relocation

While school officials initially hoped to return students to the main high school following Christmas vacation, Savage acknowledged that construction delays might push that timeline back. Project contractor Anchor Construction officials indicated that portions of the renovation may not wrap up until sometime in October at the earliest.

The Henry O. Peabody School—a vocational and technical high school connected to the main building and included in the renovation project—will also begin classes on September 9 at the Willet School, serving its 203 enrolled students. According to Peabody School Director William P. Maher, administrative letters will notify students that parts of the vocational facility may become ready between September 16 and 23, with students temporarily distributed among Willet School, Norwood Junior High in South Norwood, and Junior High North.

Budgetary Impact

School Business Administrator Stephen R. Hemman estimated that the temporary four-month relocation to Junior High North will cost the town roughly $80,000, though he cautioned that the final price tag remains fluid. While a portion of the expenses will be drawn from the school department’s $13.7 million budget, remaining costs will require funding through a special town meeting or emergency fund transfers.

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Norwood School Officials Weigh Alternatives as Renovation Delays Threaten High School Opening-August 8, 1985

    Norwood school officials discussed seven alternatives for opening day if $5 million high school renovations are not finished, while firmly rejecting double sessions.

  • Norwood Rejects Rockland Offer of Part Payment-July 16, 1985

    The summer of 1985 was a time of great economic uncertainty in Massachusetts, with the state facing significant budget deficits and high unemployment rates. However, amidst this backdrop of fiscal woes, the town of Norwood found itself embroiled in a dispute with its neighboring municipality, Rockland, over tuition fees for vocational school students. The issue…

    Stack of papers listing vocational school costs including tuition, equipment, registration, and book fees
  • Norwood High School Implements Total Smoking Ban-July 3, 1985

    In July 1985, the Norwood School Committee unanimously approved a total smoking ban at Norwood High School to begin in September, prioritizing the health of its students.

    Ashtray filled with cigarette butts labeled 'No Smoking' with people drinking and smoking in background
  • Rain-Damaged Cleveland and Prescott Schools Expected to Be Repaired by September-August 17, 1983

    Unexpected rainstorms caused roof leaks at the Cleveland and Prescott schools during active construction, though officials expect full contractor-funded repairs before the September opening.

  • School Long-Range Planning Panel to Deliver Progress Report-August 24, 1982

    Facing declining enrollments, Norwood’s school planning panel will deliver a progress report in October and final recommendations on grade configurations and potential school closures in January.

  • Norwood School Committee to Ask Teachers to Renegotiate Contracts-August 20, 1982

    Citing finance commission opposition and Proposition 2 1/2 limits, the school committee will ask teachers to renegotiate 8 percent pay raises or face town meeting review on September 20.

  • Norwood School Committee Narrows Superintendent Search to Three Finalists, Including Junior High North Principal James R. Savage-August 11, 1982

    Junior High North Principal James R. Savage was named one of three finalists for Norwood superintendent of schools, alongside Arlington assistant superintendent William J. Birmingham and Rhode Island administrator Nora M. Walker.

  • Peabody School Graduates Told Of Obligation To Support Education-June 25, 1982

    School officials emphasize community obligations and moral commitments to public education during exercises at Junior High School South.

  • Norwood School Committee Votes Eliminate Youth Hangout-July 31, 1981

    Following rampant vandalism, late-night drinking, and brush fires near Callahan Elementary School, the Norwood School Committee voted to fund a $6,000 clearing project to eliminate a notorious youth hangout.

  • School Committee Awards New Transportation Contracts-July 16, 1981

    After a difficult budget cycle in 1980, the committee avoided controversy by budgeting accurately and selecting trusted local transportation providers.