Meeting for the second consecutive week, the permanent school building construction committee voted unanimously last night to direct project architects Korslund, LeNormand and Quan (KLQ) to draft plans for a permanent roof on the fire-damaged Junior High South prior to the onset of winter.
Permanent Roof Plans and Temporary Repair Debate
The proposed roof structure is designed to protect the fire-damaged building from winter weather elements while serving permanently as the future roof for the Aaron Guild Elementary School conversion project.
Committee Chairman Ernest S. Paciorkowski initially opposed immediate construction, pointing out that over $100,000 had already been expended on temporary repairs since the structure was damaged by fire in January 1971. KLQ architect James McGrath reported that after consulting with roofing contractors, the firm determined that no contractor could finish the roof before severe winter weather set in, warning that putting the project out to bid immediately might yield no bidders. McGrath suggested opting instead for $5,000 to $10,000 in temporary repairs to the roof skylight and stairwells—the primary areas currently suffering from rain and wind penetration—while coordinating skylight removal and snow load requirements with Norwood Building Inspector John E. Grover and the state Department of Public Safety.
However, committee member Richard W. Kief strongly advocated for moving forward, arguing that waiting would jeopardize the targeted September 1973 completion date. Kief contended that even if the roof construction extended into winter, putting the project out to bid now would accelerate the overall timeline. After McGrath confirmed KLQ would attempt to complete drawings within two weeks, the committee voted unanimously to move forward.
Aaron Guild School Space Utilization and Endean Park Junior High Approval
During preliminary plan discussions for the Aaron Guild School conversion, the committee settled several space utilization debates:
- Ground Floor Layout: Voted to leave the existing shower-locker facility intact for community athletic programs, and swapped the locations of administrative offices and the instructional media center to position offices near the main entrance for security while providing natural lighting for the library.
- Classroom Additions: Rejected a proposal to add extra classroom space on the second floor above the offices, with Kief noting that reframing the area for $31,000 was cost-prohibitive since those rooms were absent from educational specifications.
- Partition Walls: Left as an alternate the demolition of eight classroom partition walls and their replacement with folding partitions, estimated at $500 for demolition per wall and $4,000 to $5,000 per folding partition, which Superintendent Dr. Philip O. Coakley and Assistant Superintendent Umberto V. Napoleone stressed were vital to meet state classroom space requirements.
In major milestone news, the permanent building construction committee announced that the School Building Assistance Bureau (SBAB) has approved final plans and specifications for the new $5.9 million junior high school slated for Endean Park. The SBAB approval guarantees the town a 65 percent construction reimbursement, shielding Norwood from a projected drop to 50 percent expected when the legislature reviews reimbursement formulas after November 1. Assistant Superintendent James R. Donovan reported that general contract bids will be received by October 11, with groundbreaking to follow weeks later. Architect McGrath noted that seven to nine contractor inquiries indicate strong bidding interest, though committee members expressed surprise that the $28,000 athletic field watering system specifications omitted an automatic grid sprinkler setup, prompting McGrath to draft a bidding alternate for an automatic system.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Permanent School Building Construction Committee Votes to Proceed with Permanent Roof Plans for Burned-Out Junior High South and Aaron Guild School-September 15, 1972
School building construction committee votes to proceed with permanent roof plans for Junior High South and Aaron Guild School, while Endean Park junior high plans secure SBAB approval.

-
Work Under Way At Junior High North-May 29, 1970
In 1970, Norwood Junior High North saw new fencing, repaving, and drainage improvements while a major school facilities survey moved toward completion, shaping long‑term planning.

-
Norwood Kills Funds For School Addition-June 26, 1969
Voters approve a $1,000 Endean Park drainage compromise and reverse a zoning rule to relocate Carl A. Johnson’s Norwood Cadillac Co. along Route 1.

-
Strikes And Weather Delay North Junior High School Construction-June 17, 1969
Superintendent Warns Of Possible Double-Session Classes If Washington Street Facility Openings Fail A steel strike at the end of last summer halted installation of metal decking for the roof and delayed the roofer. Snow and freezing weather further hampered the project before the roof could be completed at the new school site. Without a roof,…

-
Parents Challenge Junior‑High Redistricting Plan-June 12, 1969
In June 1969, furious Cleveland School families took their grievances directly to town leaders, sparking a tense debate over school enrollment, modern facilities, and neighborhood identity.

-
Superintendent Coakley Tells PTA Council That $4 Million in New School Construction Is Mandatory-September 10, 1965
Dr. Philip O. Coakley tells the PTA Council that $4 million in new school construction—including a new elementary and junior high—is mandatory to handle over-capacity enrollment.

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.