As summer drew to a close in 1964, tensions mounted on two municipal fronts in Norwood: the Oldham Building Committee prepared to weigh potential legal action against a lagging prime contractor, while the Planning Board met to overhaul official town maps to align with newly adopted zoning bylaws.

Oldham School Completion Deadlines and Contractor Dispute

The Oldham Building Committee scheduled an important evening meeting to address lingering construction deficiencies at the Oldham School, which had opened late the previous winter amid ongoing disputes. Two strict completion deadlines had been imposed by the committee on July 6 upon prime contractor Melvin Goverman, acting on the advice of project architects Stoner Associates.

While an August 21 deadline for interior alterations—covering unfinished interior walls, doorways, floors, the boiler room, and various internal spaces—had already passed without formal administrative retaliation, the committee granted Goverman an extension to September 15 to complete outstanding exterior projects, which largely involved drainage and landscaping work.

Although committee chairman Joseph Olshan was temporarily out of state, School Superintendent Dr. Philip O. Coakley and fellow building committee members confirmed that tonight’s meeting would proceed as planned. Architects and committee members cautioned that failure to meet the final mid-September deadline to their satisfaction could trigger formal court action against the contractor.

Planning Board Reviews Town Map Changes and Dedham Builder Easement

Concurrently, the Planning Board convened under Chairman James T. O’Sullivan to review extensive updates required to bring the official town map into strict conformity with Norwood’s newly adopted zoning bylaws. The review encompassed the elimination of a designated “trunk highway” and the precise redefinition of residential and industrial zones. Board member Francis Wisgirda also presented findings on recodifying town bylaws for enhanced clarity, with officials anticipating that the comprehensive zoning adjustments would be finalized within six months ahead of the following year’s town meeting.

Additionally, the board scheduled discussions with Dedham contractor Paul Stivaletta regarding a proposed utility easement for his planned development on Neponset Street. An earlier municipal attempt to grant Stivaletta access to existing water and sewer lines had fallen through, prompting the board to explore easement solutions before presenting final recommendations.

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Norwood Kills Funds For School Addition-June 26, 1969

    Voters approve a $1,000 Endean Park drainage compromise and reverse a zoning rule to relocate Carl A. Johnson’s Norwood Cadillac Co. along Route 1.

    Open ledger titled County Ledger 1969 with budget requests marked 'Budget Cut' and a judge's gavel on a wooden desk
  • Strikes And Weather Delay North Junior High School Construction-June 17, 1969

    Superintendent Warns Of Possible Double-Session Classes If Washington Street Facility Openings Fail A steel strike at the end of last summer halted installation of metal decking for the roof and delayed the roofer. Snow and freezing weather further hampered the project before the roof could be completed at the new school site. Without a roof,…

  • Parents Challenge Junior‑High Redistricting Plan-June 12, 1969

    In June 1969, furious Cleveland School families took their grievances directly to town leaders, sparking a tense debate over school enrollment, modern facilities, and neighborhood identity.

  • Willett School Wiring Dispute Adds $9,000 to Construction Costs Ahead of September Opening-July 28, 1968

    ⠀ The Norwood Permanent Building Construction Committee last night voted to approve the installation of additional circuit breaker panels so that the Willett School can open on schedule in September. The cost of the electrical installation is estimated at approximately $9,000. William J. Kates, supervisor of the Municipal Light Department and inspector of wires, advised…

  • Ground Broken for $1.23 Million George F. Willett Elementary School-August 11, 1967

    Following a $1.04 million contract award and emergency state borrowing approval, Rocheford Construction Co. broke ground on the 16-classroom George F. Willett Elementary School.

  • School Building Committee Votes to Recommend Addition to Cleveland School-August 16, 1963

    By a 3-2 vote, Norwood’s Elementary School Building Committee recommended an eight-room addition to the Cleveland School rather than constructing a new facility on Wilson Street.

  • School Committee Considers New School Sites-March 22, 1962

    NORWOOD, Mar, 22 -Arthur B. Rodgers, chairman of the School Housing Study Committee which is responsible for the long-range projection of the towns future school needs, has requested information from the School Committee on its plans for new schools. Being considered by the School Committee are the possibilities of the construction of a second junior…

  • Redecorating Of School Interiors Is Recommended-February 9, 1950

    Purchase Of Land For New Stands At High School Also Urged By Supt. Lynch Recommendations for the improvement of the present school plant before the town faced with the problem of new construction were advanced by School Superintendent Lincoln D. Lynch, as principal speaker at the February meeting of the Chamber of Commerce Tuesday night…


Discover more from Norwood Historical Society

Subscribe to get the latest posts sent to your email.

Leave a Reply

This site uses Akismet to reduce spam. Learn how your comment data is processed.