School Committee Considers Innovative Grade Reorganization and High School Expansion

During a session of the Norwood School Committee last night, committeeman William Egan introduced a proposal to adopt a “middle school” class pattern for the town’s educational system. Following his proposal last week to construct a new $4.5 million, 2,000-pupil senior high school to counter surging population growth, Egan suggested utilizing the existing junior high school as a centralized middle school exclusively housing all sixth-grade students.

Under Egan’s proposed framework, seventh and eighth grades would relocate to the proposed senior high school building, creating a four-year senior high facility, while the current junior high would transition into the middle school. Egan argued that grouping all sixth graders together would alleviate overcrowding in elementary schools and eliminate the immediate necessity of constructing an additional elementary building.

Committee Debate & Leadership Perspectives

Superintendent and Committee Reactions

  • Superintendent Philip O. Coakley: Opposed the middle school concept, stating he saw no advantage to the model and would instead prefer building an additional elementary unit while utilizing both present junior and senior high facilities as two intermediate units. However, Coakley expressed favorable views toward a larger senior high school.
  • Mrs. Mary Bemman: Criticized Egan’s middle school theory, warning that the close interpersonal relationships sought for elementary students could suffer, and expressed disappointment that the plan was aired without prior committee consensus.
  • Francis X. Sheehan & Joseph Curran: Supported reviewing all housing possibilities beforehand so the committee is fully prepared to address questions on the town meeting floor.

School Needs Study & Site Selections

  • Study Group: Headed by **Walter Gotovich**, the committee was empowered by town meeting to analyze all foreseeable school needs and report findings by year’s end.
  • Playground Sites: Chairman **Henry Diggs** was authorized to confer with Town Counsel regarding the status of land behind **Father MacAleer’s Playground** and the **Wilson Street Playground**, considered prime locations for upcoming school construction (with Wilson Street slated for the elementary unit).

No Immediate Action Taken as Broader Study Continues

The School Committee took no formal action on Egan’s middle school or senior high expansion proposals last night, preferring to let the school needs study group complete its comprehensive evaluation.

Meanwhile, community events highlighted in local reports included an upcoming Norwood Camera Club regional color slide exhibition at Norwood High School headed by club president Charles Lennon (with judges Peggy Jordan, Thomas J. Lowe, and Marion M. Rich), and the launch of the local Arthritis Foundation campaign led by area chairman Herbert L. Newman.

Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger

More…

  • Gridlock Over $6-Million Junior High Rebuilding Plan and Norwood Arena Noise-This Day in Norwood History-June 27, 1971

    A dual crisis hits Norwood in 1971 as a $6-million junior high deficit triggers political warfare and state experts condemn racetrack noise.

    Teacher writing school budget details on chalkboard with students listening and thinking about funding issues
  • Officials Weighing School Repair Cost-March 6, 1971

    Selectmen last night favored start on work to secure walls of the fire-gutted third story of Norwood Junior High School South which are still standing after a section of the rear wall collapsed Thursday. Architect’s Proposal The local architectural firm of Korslund, LeNormand and Quann, Inc., which directed the construction of the temporary roof damaged…

  • Independent School Survey Recommends $21.8 Million Building Program, Terming Norwood Schools ‘Critically Overcrowded’-September 17, 1970

    An independent master plan by Arthur D. Little recommends a $21.8 million building program to combat critical overcrowding across all Norwood school levels.

  • Work Under Way At Junior High North-May 29, 1970

    In 1970, Norwood Junior High North saw new fencing, repaving, and drainage improvements while a major school facilities survey moved toward completion, shaping long‑term planning.

  • Norwood Junior High School to Institute Double Sessions This Fall-August 20, 1969

    Citing equipment and installation delays that will keep Junior High School North closed until November, the Norwood school board voted to implement double sessions at the old facility.

  • Norwood Kills Funds For School Addition-June 26, 1969

    Voters approve a $1,000 Endean Park drainage compromise and reverse a zoning rule to relocate Carl A. Johnson’s Norwood Cadillac Co. along Route 1.

    Open ledger titled County Ledger 1969 with budget requests marked 'Budget Cut' and a judge's gavel on a wooden desk
  • Permanent Building Committee Unveils High School Addition Cost Estimates-June 13, 1969

    Finance Commission Reviews Extensive School Expansion Proposals Ahead of Critical Monday Town Meeting Warrant Meeting late last night with the Finance Commission (FinCom), the Permanent Building Construction Committee formally quoted detailed cost estimates regarding the highly anticipated Norwood High School addition project. The comprehensive structural estimates are being prepared for immediate presentation to town representatives,…

  • Willett School Wiring Dispute Adds $9,000 to Construction Costs Ahead of September Opening-July 28, 1968

    ⠀ The Norwood Permanent Building Construction Committee last night voted to approve the installation of additional circuit breaker panels so that the Willett School can open on schedule in September. The cost of the electrical installation is estimated at approximately $9,000. William J. Kates, supervisor of the Municipal Light Department and inspector of wires, advised…

  • Permanent Building Committee Warns of Cost Overruns for New Junior High School as Subcontract Bids Exceed Estimates-October 27, 1967

    Subcontract bids for Norwood’s new 117,110-sq-ft junior high school totaled $1.14M, prompting building committee members to warn of necessary town meeting budget increases.

  • Ground Broken for $1.23 Million George F. Willett Elementary School-August 11, 1967

    Following a $1.04 million contract award and emergency state borrowing approval, Rocheford Construction Co. broke ground on the 16-classroom George F. Willett Elementary School.