Reopening Target Set for Mid-November Following Construction Delays
Students attending the Henry O. Peabody vocational school may finally return to their classrooms by mid-November, according to estimates discussed at last night’s permanent building construction committee meeting. While project manager John Sosnowski of Anchor Construction of Lowell—the general contractor handling the $5 million renovation of the high school and the adjacent Peabody facility—maintained the building could be ready by November 8, committee members advised a more conservative timeline.
“Realistically, you’re not looking at anything earlier than Nov. 15, and probably Thanksgiving week,” stated committee member Roger Pelletier. Furthermore, architect Richard Heydecker of Korslund, LeNormand & Quann noted that a final post-construction cleanup will require an additional three to seven days.
The extensive renovation project was originally slated for completion on August 30. Because that deadline was missed, the school department had to scramble to find temporary alternative class spaces for the approximately 175 displaced Peabody students, scattering them between Junior High South and the Willett school—arrangements that both administrators and students have criticized as inadequate.
Permanent Building Committee Withholds $37,000 Over Defective Athletic Fields
In addition to delays at the vocational school, tensions flared regarding the high school renovation project. The construction committee voted to withhold approximately $37,000 in payments to Anchor Construction due to severe dissatisfaction with the newly redesigned football field and running track.
High School Athletic Director Arthur Gulla detailed a litany of complaints, pointing out that the field lacks proper grading and the necessary dome-topped curvature required for adequate drainage and turf protection, resulting in poor sod growth. Gulla warned that correcting the issues will cost two growing seasons. In the meantime, the school department is absorbing a $4,500 annual transportation expense to bus football players to Junior High South for practices, while playing all games entirely away from home.
“We’re spending $4,500 to transport kids to practice, and we probably will next year too,” Gulla said. “We’re playing all our games away—it’s not fair to the kids.” While Sosnowski defended the grading as correct, he agreed that a professional surveyor will evaluate the field the following week to determine whether regrading is necessary.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
Joseph Katchpole Succeeds George Usevich as Vice Principal of Norwood High School-August 23, 1990

Health and physical education department head Joseph Katchpole has been named acting vice principal of Norwood High School, succeeding George Usevich in the school administration.
-
Norwood to Sue Blue Hills School to Block Budget-July 19, 1990

The town of Norwood was on a collision course with the Blue Hills Regional Technical School in July 1990, as officials prepared to file a lawsuit to block the school’s revised budget for the upcoming academic year. The dispute had been brewing for several weeks, ever since the four district towns – Norwood, Holbrook, Dedham,…
-
Oldham School Portable Classroom Nears Completion-October 12, 1989

Norwood’s Oldham School prepares to open a long-awaited portable classroom by month’s end, and veteran teacher Thomas MacDonough recounts his educational fellowship in West Germany.
-
Newcomers Learn to Take Middle School in Their Stride-September 7, 1989

Transitioning from elementary school to middle school can be an intimidating milestone for any young student, but as classes officially got underway this week, Norwood’s newest middle schoolers quickly learned to take the change in stride. Navigating larger hallways, adjusting to rotating class schedules, and meeting new teachers mark a major rite of passage for…
-
First Day of School Brings Excitement and New Beginnings for Norwood’s Class of 1999-September 10, 1987

Norwood students return to class for the 1987-88 school year, marking the first day of school for the Balch Elementary first-graders who make up the graduating class of 1999.
-
Balch and Norwood High Welcome Students on the First Day of School for the Class of 1999-September 10, 1987

Balch Elementary and Norwood High welcome students back for the 1987-88 academic year, marking the first day of school for the graduating Class of 1999.
-
Norwood High Teachers to Implement Uniform Curriculum Guides Starting Next Week-September 3, 1987

When classes resume next week, high school teachers across Norwood will officially be “going by the book.” Superintendent of Schools James Savage informed the school committee that faculty members teaching every course—from woodshop to algebra—will be required to follow newly established, standardized curriculum guides authored by Norwood educators. Closing the Gap in District Education The…
-
$16,600 Grant Equips New Norwood High School Cable Television Studio-August 18, 1987

Norwood Community Television awarded a $16,600 grant to equip a new student-run television studio at Norwood High School, expanding local cable programming and production training.
-
Norwood High School Releases Fourth-Quarter Honor Roll-August 14, 1986

Norwood High School announced its student honor roll for the fourth quarter of the 1985-1986 academic year, recognizing academic achievement across senior, junior, and sophomore classes.
Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.