Regional Aviation Officials Pledge Priority Support for Cracked 4,000-Foot Strip as Commission Chairman Bristles Over Oct. 15 Crash Remarks
NORWOOD – Federal Aviation Administration (FAA) officials reaffirmed strong backing on Tuesday, November 17, 1981, for a proposed $1.7 million capital improvement package at Norwood Memorial Airport, expressing optimism that federal funding would become available the following year to reconstruct the airport’s deteriorating main runway. Reported by Patriot Ledger reporter Rick Moriarty on Wednesday, November 18, 1981, regional FAA leaders from the New England office in Burlington met with the Norwood Airport Commission at Town Hall alongside Massachusetts Aeronautics Commission Chief Airport Engineer Dominic R. DiVirgilio Jr., Airport Manager John Dalton, and engineers from Boston-based Metcalf & Eddy Inc., the consulting firm chosen to design the runway reconstruction.
While the exact federal funding share and release timeline remained subject to congressional appropriations—likely not before the following summer—Airport Commission Chairman Wilfred C. Chesebrough warned that failing to secure federal aid could force closure of the 4,000-foot main landing strip, which engineers noted had grown severely cracked across 39 years of service. Gerald D. Curtin, chief of the airports division in the regional FAA office, pledged unequivocal backing: “I think I can assure you that I will support the runway improvement project—the FAA will support it. Reconstruction of that runway has to be one of the highest priority projects around.” Vincent A. Scarano, head of program and planning in Curtin’s division, noted that Norwood had sat atop the FAA’s priority list for three consecutive years as the region’s most important reliever airport for Logan Airport traffic, adding that while Norwood might not receive every dollar of its $1.7 million request, it could anticipate a substantial portion.
Scarano outlined two paths for the commission: wait until federal funds were formally allocated, or proceed immediately with preliminary engineering in hopes of later reimbursement. With Metcalf & Eddy scheduled to submit its engineering scope and fee proposal on December 2, Chesebrough urged the five commissioners present to break a 3-3 deadlock from the prior week and tap a portion of the commission’s $48,000 reserve for preliminary land surveys and planning before winter weather halted outdoor field work, warning the board risked losing momentum. He held off pushing a vote, however, after Commissioner Pauline M. Grassos objected that voting without the two absent commissioners would be unfair.
Tensions briefly flared during the conference when Curtin brought up a rocky ledge near one end of the runway—an obstacle estimated to cost roughly $42,000 to remove, either under the $1.7 million project or earlier if the FAA funded new approach lights—remarking that the October 15 crash-landing of a twin-engine aircraft at the airport underscored the value of clearing it. “I’m sorry, that’s an extremely sore toe,” Chesebrough shot back, prompting Curtin to clarify, “I didn’t mean to imply that ledge caused the accident,” only that the FAA had long wanted the ledge removed. While the pilot who survived the dense-fog crash, the Rev. John T. Lawler, had publicly faulted the commission for lacking landing aids and an officer of the Norwood Airport Association had partially blamed the ledge, Chesebrough rejected any liability, insisting the commission had never refused funds for ledge removal and citing Airport Manager Dalton’s crash report indicating the plane may have clipped approach lights without mentioning any impact with the ledge.
1981 Norwood Airport Project Figures Adjusted to 2026 Dollars & Site Legacy
Inflation-adjusted using U.S. Bureau of Labor Statistics CPI data ($1.00 in Nov. 1981 ≈ $3.54 in 2026)
| 1981 Airport Project / Reserve Item | 1981 Amount | 2026 Equivalent |
|---|---|---|
| Proposed Airport & Main Runway Reconstruction | $1,700,000 | ~$6,018,000 |
| Commission Engineering & Planning Reserve | $48,000 | ~$169,920 |
| Estimated Runway End Ledge Removal Cost | $42,000 | ~$148,680 |
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Turn The First Sod For Norwood Airport-This Day In Norwood History-February 3, 1931
Work on the new Norwood Airport started with much activity yesterday morning, when two steam shovels began operations and a fleet of trucks were filling the large stretch of meadow land, off Neponset St. Many citizens, engineers and aviators were present when the ground was broken. After the proposed layout was shown by Robert S.…