NORWOOD — An eleventh-hour session of the Oldham School Building Committee is being held tonight to make the decisive call on whether the newly constructed school will officially open its doors for student registration tomorrow morning.
Final Scramble and Boiler Inspections
Workmen labored through the weekend, including a full day on Saturday, trying to wrap up numerous minor finishing tasks alongside major repair and painting demands insisted upon by the building committee, whose members conducted a thorough inspection of the premises over the weekend.
Of prime concern to both the school committee and the building committee is official approval of the school’s heating system. Boiler safety tests—originally scheduled for Friday—were forced to cancel due to a lack of electric power, which was finally restored on a temporary basis Friday by employees of the Norwood Light Department following a spirited push by committee members to accelerate lagging construction. A representative from the Department of Public Safety was slated to arrive at the Prospect Street school for the boiler test, as state occupancy approval is mandatory before the school can open. Additionally, the Norwood Fire Department must sign off on vital safety factors, including the heating system.
Unfinished Construction and Dissenting Voices
The greatest concentration of unfinished work centers on the kindergarten rooms, which were originally scheduled to open Monday, along with uninstalled carpeting in the principal’s office, teachers’ rooms, and the library, plus considerable interior and exterior tile work. Furthermore, about 1,600 square feet of tile flooring deemed “unsatisfactory” by the building committee must be replaced by general contractor Goverman at their own expense, though Clerk of the Works William Snyder reported that replacement work will be conducted in stages to avoid an unsightly appearance.
Despite Building Committee member Arthur Rodgers and Mrs. Ellen Dixon strongly opposing opening the school under any unfinished conditions—even discussing involving the bonding company—the building committee ultimately voted unanimously during its Wednesday night meeting to proceed with plans to open. Clerk of the Works Snyder privately expressed his opinion that the building is still roughly two to three weeks away from being fully complete.
Meanwhile, school department custodians worked feverishly over the weekend moving furniture into classrooms and conducting a deep cleaning. While exterior landscaping, hot-top walkways, and driveways are nearly finished, much of the remaining site work and classroom tile replacement will be handled after school hours. If the heating system passes state and local inspections, approximately 450 students are expected to walk through the doors tomorrow morning.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
More…
-
Norwood School Committee Narrows Superintendent Search to Three Finalists, Including Junior High North Principal James R. Savage-August 11, 1982
Junior High North Principal James R. Savage was named one of three finalists for Norwood superintendent of schools, alongside Arlington assistant superintendent William J. Birmingham and Rhode Island administrator Nora M. Walker.

-
Peabody School Graduates Told Of Obligation To Support Education-June 25, 1982
School officials emphasize community obligations and moral commitments to public education during exercises at Junior High School South.

-
Superintendent Taris Seeks to Curb Rising Costs of After-Hours School Building Use-September 4, 1981
Superintendent of Schools Louis J. Taris is pushing to rein in the surging volume of outside organizations utilizing school facilities during evening and weekend hours, citing mounting financial burdens on the school department. Dr. Taris informed the school committee that dozens of local organizations currently utilize school buildings after hours, frequently without paying any rental…

-
Norwood School Committee Votes Eliminate Youth Hangout-July 31, 1981
Following rampant vandalism, late-night drinking, and brush fires near Callahan Elementary School, the Norwood School Committee voted to fund a $6,000 clearing project to eliminate a notorious youth hangout.

-
School Committee Awards New Transportation Contracts-July 16, 1981
After a difficult budget cycle in 1980, the committee avoided controversy by budgeting accurately and selecting trusted local transportation providers.

-
Norwood School Board Rejects All Special Needs Busing Bids-August 21, 1980
With opening day just two weeks away, the Norwood School Committee voted 4-3 to reject all bids received the previous week for special needs student transportation. Acting under emergency procedures, the board announced it will call for new bids by Tuesday, with a potential contract award scheduled for Wednesday night. The rejected proposals came from…

-
Henry O. Peabody School Director Ruth Shea Ponders Retirement After 14 Years-August 12, 1980
After 14 years expanding vocational education, Henry O. Peabody School director Ruth Shea ponders retirement while securing a 97 percent graduate job placement rate.

-
Norwood School Administration Relocates to Willett School-July 24, 1980
The Norwood School Administration relocated to the George F. Willett School and enacted strict new graduation credit requirements.

Discover more from Norwood Historical Society
Subscribe to get the latest posts sent to your email.