The Aaron Guild School doors will open in September to two new tenants as Norwood selectmen voted unanimously last night to lease the building for one year to the Norwood CETA Consortium and the Educational Collaborative of Greater Boston (EdCo) for a total rent of $148,000. In doing so, the board rejected for the time being a proposal to move the town’s Civic Recreation Center into the ground floor of the three-story building. Arguing that the town needed time to determine a long-range use for the school—which was closed in June due to declining enrollment—Town Manager John J. Carroll and Joan H. Cuff, chairman of the Guild Study Committee, recommended the two short-term leases.
This is a temporary expediency; it will give us security and occupancy, Selectmen Chairman Joseph F. Curran told the sixty-five residents at the meeting. However, Walter J. Grady, chairman of the Civic Replacement Committee, had urged the board to reserve the ground floor for recreation facilities to replace the Civic Center. Following the meeting, he stated, This is the first step toward losing our Civic Center. If we lose the Aaron Guild, we will never have a central recreation facility. Walter J. Grady called the decision a bad business transaction, arguing that delaying action for a year will decrease the buying power of the $2 million Norwood Hospital is paying to replace the recreation facilities. The town has agreed to sell the present Civic Center, located across the street from the Guild School, to the hospital once its expansion plans are approved by the state.
Long-delayed state approval is expected around August 14, and hospital officials are considering offering financial incentives to vacate the Civic as soon as possible. Hospital Administrator David P. Buchmueller stated that one possible incentive would be to pay the town $10,000 per month for each month earlier than the twenty-one-month deadline that the Civic is vacated. While Walter J. Grady contended this incentive could offset the rent, Town Manager John J. Carroll dismissed the proposed schedule as totally unrealistic, noting it takes three or four months to hire an architect-consultant.
Under the approved terms, CETA will occupy the first and second floors starting October 1 on a full-year lease for $117,000, while EdCo will take over the ground level (except for the auditorium-gymnasium) starting September 1 on a ten-month lease for $31,000. Representatives of both tenants confirmed they could vacate when the leases expire if required. CETA, presently located on Davis Avenue, will use the larger quarters to expand vocational training programs under Executive Director Larry Fitch, while EdCo will use six classrooms to work with about thirty severely handicapped students from the Wrentham and Fernald state schools. Selectman Joseph F. Curran noted that other proposed uses, such as a police sub-station and a drop-in center for the elderly, will be considered when permanent plans are developed. Selectman Mary J. Fox was absent from the unanimous vote.
Archival Note: This article has been dynamically reconstructed from the original public record print archives of the Patriot Ledger
-
Balch and Norwood High Welcome Students on the First Day of School for the Class of 1999-September 10, 1987

Balch Elementary and Norwood High welcome students back for the 1987-88 academic year, marking the first day of school for the graduating Class of 1999.
-
Norwood High Teachers to Implement Uniform Curriculum Guides Starting Next Week-September 3, 1987

When classes resume next week, high school teachers across Norwood will officially be “going by the book.” Superintendent of Schools James Savage informed the school committee that faculty members teaching every course—from woodshop to algebra—will be required to follow newly established, standardized curriculum guides authored by Norwood educators. Closing the Gap in District Education The…
-
$16,600 Grant Equips New Norwood High School Cable Television Studio-August 18, 1987

Norwood Community Television awarded a $16,600 grant to equip a new student-run television studio at Norwood High School, expanding local cable programming and production training.
-
Norwood High School Releases Fourth-Quarter Honor Roll-August 14, 1986

Norwood High School announced its student honor roll for the fourth quarter of the 1985-1986 academic year, recognizing academic achievement across senior, junior, and sophomore classes.
-
150 Norwood High Students Walk Out and March to Protest $5 Million Renovation Delays-October 31, 1985

Protesting ongoing delays in a $5 million renovation project that has kept them displaced at Junior High North, 150 Norwood High students staged a walkout and marched to the high school.
-
Norwood High SAT Scores Surge as Principal John Piccirilli Commends Student Gains-October 30, 1985

Driven by a 12-point surge in verbal scores and math averages exceeding state and national benchmarks, Norwood High Principal John Piccirilli celebrated strong college board gains.
-
School Opening Delayed for High School Students-August 27, 1985

Norwood high school classes are delayed to September 9 as students temporarily relocate to Junior High North during a $5 million renovation project.
-
High School Students to Relocate to Vacant Junior High School North-August 21, 1985

Citing extensive construction delays by Anchor Construction Co., Norwood school officials voted to move nearly 950 high school students to Junior High School North for the start of the school year.
-
Norwood School Officials Weigh Alternatives as Renovation Delays Threaten High School Opening-August 8, 1985

Norwood school officials discussed seven alternatives for opening day if $5 million high school renovations are not finished, while firmly rejecting double sessions.