Low Bidders of Two To Get Contract For Project To Start Soon
The Norwood selectmen approved a resolution awarding the contract for the water tank and tower P. W. A. project to the Chicago Bridge and Iron Company on Tuesday night. The resolution adopted by the Board must be approved by the regional director of the P. W. A. before the contract can be awarded.
The Chicago Bridge and Iron Company was the low bidder of two on the job with their figure $52,535.00, and the Board’s resolution quoting this fact and the fact that in its estimation the Company is financially responsible and competent to complete the work in a satisfactory manner, awarded tho contract to them. Work on the project is expected to begin early in December.
(All articles originally published in the Norwood Messenger)
Town Meeting Votes to Replace Both Water Towers-This Day In Norwood History-November 1, 2023
Town Meeting members approced a major infrastructure project to replace its two aging water storage tanks, located between Highland Cemetery and Norwood High School. These tanks, a 4-million-gallon steel reservoir … Continue reading Town Meeting Votes to Replace Both Water…
Vote For Consulting Engineering Service On Water Tank, Tower-This Day In Norwood History-September 16, 1938
SELECTMEN TAKE ACTION ON TWO PWA PROJECTS TUESDAY The Norwood Board of Selectmen took action relative to the two P.W.A. projects which have been approved by Washington on Tuesday night, … Continue reading Vote For Consulting Engineering Service On Water…
Special Meeting Votes On Water Tower-This Day In Norwood History-September 6, 1938
Article 4. To see if the Town will vote to raise and appropriate a sum of money for the purpose of constructing a water storage tank and tower with piping … Continue reading Special Meeting Votes On Water Tower-This Day…